Generating Unit Outage Report for 22-02-2012

A. Planned Outages
S.NoStationLocationOwnerUnit NoCapacityReason(s)OutageExpected Revival Date
DateTime
  Central Sector (CS)
1RAPS-ARAJASTHANNPC1100Subject to regulatory clearance.09-10-200422:58-
2Bhakra-L HPSHPBBMB2108Upgradation work.26-04-201008:0031-03-2012
3Bhakra-L HPSHPBBMB5108Upgradation work.22-12-201013:3030-04-2012
4Dehar HPSHPBBMB5165Annual maintenance.01-10-201110:0003-03-2012
5Bhakra-L HPSHPBBMB1108Annual maintenance.10-02-201211:1027-02-2012
6Dulhasti HPSJKNHPC3130Heavy leakage in MIV downstream seal.14-02-201200:0002-03-2012
7Dulhasti HPSJKNHPC2130Heavy leakage in MIV downstream seal.14-02-201200:0002-03-2012
8Dulhasti HPSJKNHPC1130Heavy leakage in MIV downstream seal.14-02-201200:0002-03-2012
9Dehar HPSHPBBMB6165Annual maintenance.17-02-201218:0023-02-2012
10Auraiya GPSUPNTPC1111.19Closed by station due to less requisition by states.17-02-201223:10-
11Dadri GPSUPNTPC4130.19For flame tube inspection.18-02-201206:0028-02-2012
 Sub Total(CS)  1385.38 
  State Sector (SS)
1Guru Nanak Dev TPS (Bhatinda)PUNJABPSEB3110Upgradation work.29-12-200900:00-
2Paricha TPSUPUPRVUNL2110Renovation and maintenance05-01-201107:52-
3Guru Nanak Dev TPS (Bhatinda)PUNJABPSEB4110Renovation and maintenance work.05-11-201117:10-
4Panipat TPSHARYANAHPGCL2110Maintenance & Renovation work.20-12-201103:25-
5Panipat TPSHARYANAHPGCL6210Annual maintenance.07-02-201202:0205-03-2012
6RGTPP( Khedar)HARYANAHPGCL2600General maintenance.21-02-201205:3012-03-2012
 Sub Total(SS) 1250 
Total Planned Outage (CS+SS): 2635.38

B. Forced Outages
S.NoStationLocationOwnerUnit NoCapacityReason(s)OutageExpected Revival Date
DateTime
  Central Sector (CS)
1Shree Cement (IPP) TPSRAJASTHANCSL2150Turbine bearing Problem.18-01-201210:4625-02-2012
2NAPSUPNPC1220Turbine Problem. Manually tripped & taken under shut down.19-01-201214:3224-02-2012
3Barsingsar (IPP) LTPSRAJASTHANNLC2125Wet material leakage.14-02-201221:49-
4ISTPP (Jhajjar)HARYANANTPC1500Electrical fault. Problem in turbine17-02-201209:32-
 Sub Total(CS) 995 
  State Sector (SS)
1Obra TPS UPUPRVUNL11200Turbine problem.10-07-201120:53-
2DCRTPP (Yamuna Nagar)HARYANAHPGCL2300Electrical fault25-09-201110:31-
3Paricha TPSUPUPRVUNL4210Bearing problem.19-12-201108:02-
4Anpara-C TPSUPLANCO2600Coal shortage07-02-201217:24-
5Giral (IPP) LTPSRAJASTHANRRVUNL2125Boiler tube leakage.14-02-201206:43-
6Giral (IPP) LTPSRAJASTHANRRVUNL1125Cooling water pump vrust15-02-201210:30-
7Bawana GPSDELHIDTL1220Load commutated inverter shifting.19-02-201205:45-
8Suratgarh TPS RAJASTHANRRVUNL1250Generator Fault.20-02-201214:12-
 Sub Total(SS)2030 
Total Forced Outage (CS+SS): 3025

Regional Generation Outage Summary (MW)
Central SectorState SectorRegional Total Outage(MW)
PlannedForcedTotal(CS)PlannedForcedTotal(SS)
1385.389952380.381250203032805660.38

C. Generating Units Revived during last day which were out before 22-02-12
S.NoStationLocationOwnerUnit NoCapacityReason(s)OutageRevival
DateTimeDateTime
  Central Sector (CS)
1Singrauli STPSUPNTPC5200Due to Overhauling of machine.11-01-201202:2422-02-201217:16
2URI HPSJKNHPC1120Annual maintenance.14-02-201210:1022-02-201215:12
3Chamera-I HPSHPNHPC3180Annual maintenance.19-02-201211:0022-02-201218:00
4Badarpur TPSDELHINTPC3100Closed by DTL due to less demand.21-02-201212:0822-02-201206:40
 Sub Total(CS) 600 
  State Sector (SS)
--No Outages--
 Sub Total(SS) 0 
Total (CS+SS): 600

D. Short Duration Outages during the day
S.NoStationLocationOwnerUnit NoCapacityReason(s)OutageRevival
DateTimeDateTime
  Central Sector (CS)
--No Outages--
 Sub Total(CS) 0 
  State Sector (SS)
--No Outages--
 Sub Total(SS) 0 
Total (CS+SS): 0