Transmission Elements Outage Report for 24-05-2013

A. Details of Transmission Elements under Planned Outage:-
S.NoElement NameTypeVoltage LevelOwnerOutageRevivalExpected Date of RevivalReason / Remarks
DateTimeDateTime
1Agra-FatehpurLine765 kVPGCIL24-05-201307:1724-05-201320:42-For replacement of porcelain disc insulators with polymer insulators strings.and other rectification works .
2Mohindergarh-Mundra Pole 2Line500 kV HVDCAPL24-05-201306:2924-05-201313:01-Replacement of CT.
3Vindhyachal HVDC BtB Block 1HVDV Station500 kV HVDCPGCIL23-05-201314:31**25-05-2013For change of strung BUS for accommodating 2nd Bus Reactor at Vindhyachal
4Gurgaon-Manesar 1Line400 kVPGCIL06-03-201312:42**31-05-2013Bay extension work at GIS Gurgaon.
5Uri-II(NHPC)-Wagoora(PG)Line400 kVPGCIL02-05-201317:55**31-05-2013General maintenancein GIS s/yard by NHPC
6Balia-Patna 3Line400 kVPGCIL24-05-201305:5224-05-201319:52-Constrution of new bay at Patna.
7Balia-Patna 4Line400 kVPGCIL24-05-201305:5224-05-201320:11-Constrution of new bay at Patna.
8Lucknow(PG)-Sultanpur(UP)Line400 kVUPPTCL24-05-201308:1324-05-201319:47-For cleaning of disc insulators and other preventive maintenance works in the line and sstn ends by UPPCL.
9Moga 250 MVA ICT 3ICT400/220 kVPGCIL17-05-201311:19**02-06-2013For replacement of this 250MVA ICT with other new ICT of 500MVA.
10Patiala 500 MVA ICT 3ICT400/220 kVPGCIL20-05-201306:45**28-05-2013For Lead modification work in this ICT of 500 MVA.
11Khodri(UPCL)-Saharnpur(UPPCL)-2Line220 kVUPPTCL21-05-201306:15**NAFor Xing/Stringing works of LILO of Khara-Saharanpur line (to be LILOED at Behat) between loc. no. 3 & 4.
*-Line still under outage     NA - Not Available

B. Details of Transmission Elements under Forced Outage:-
S.NoElement NameTypeVoltage LevelOwnerOutageRevivalExpected Date of RevivalReason / Remarks
DateTimeDateTime
1Unnao C 1000 MVA ICT 1ICT765/400 kVUPPTCL24-05-201311:4324-05-201313:39-TO ATTEND DEFFECTIVE ISOLATOR
2Chabra-Hindaun IILine400 kVRRVPNL21-05-201319:59**NACT of Bus coupler damaged at Bhilwara (RRVPN)
3Daultabad(HVPNL)-Jhajjar(APCPL) 1Line400 kVHVPNL24-05-201316:0724-05-201317:32-Tripped during Busbar protection Testing.
4Daultabad(HVPNL)-Jhajjar(APCPL) 2Line400 kVHVPNL24-05-201316:0724-05-201318:02-Tripped during Busbar protection Testing.
5Amritsar-JalandharLine400 kVPGCIL24-05-201317:0724-05-201317:22-Phase to earth faultManually Tripped due to Flash over in Bus isolator.
6Rishikesh 240 MVA ICT 2ICT400/220 kVUPCL25-10-201119:25**NAICT burnt.
7Jodhpur II 315 MVA ICT 1ICT400/220 kVRRVPNL20-05-201309:02**30-06-2013B-ph bushing damaged.
8 Bareilly 50 MVAR B/RBus Reactor400 kVUPPTCL05-08-200700:00**NAFailure of Reactor.
9 Lucknow 50 MVAR B/RBus Reactor400 kVUPPTCL10-07-200800:46**NAFailure of Reactor.
10 Sarnath 50 MVAR B/RBus Reactor400 kVUPPTCL16-02-200906:14**NAFailure of Reactor.
11Panipat 71.66 MVAR B/RBus Reactor400 kVBBMB06-02-201200:11**01-09-2013Damaged and to be replaced by New .
12Fatehpur(UP)-Unchahar(NTPC) 2Line220 kVUPPTCL24-05-201308:4324-05-201315:07-.
*-Line still under outage     NA - Not Available

C. Details of Transmission Elements Opened manually due to High Voltage:-
** - Line shall be closed subject to voltage permissibility