Select Month Select Year For 18-Nov-2017 For 19-Nov-2017

STOA Scheduling Acceptance for November 2017

    Colored transactions are Revised/Surrendered
 
S.No Acceptance No Application no Utilities FromDate ToDate Schedule Route
1Nov-17/AP-45416-SD
17-Nov-17
APPCPL/67/2456
dt17-Nov-17
APPCPL
JHABUA
-NPCL(UP)
18-Nov-17 18-Nov-17 0000-1000: 0 MW
1000-1700: 10 MW
1700-2400: 0 MW
WR-NR
2Nov-17/AP-45415-SD
17-Nov-17
NPCL/APPCPL/181117
dt17-Nov-17
NPCL(UP)
HPPC
-NPCL(UP)
18-Nov-17 18-Nov-17 0000-0100: 26 MW
0100-0200: 21 MW
0200-0400: 16 MW
0400-0500: 10 MW
0500-0600: 21 MW
0600-0700: 42 MW
0700-0800: 36 MW
2000-2200: 50 MW
2200-2300: 48 MW
2300-2400: 37 MW
----
3Nov-17/AP-45404-FS
17-Nov-17
GBHPL/UPCL/21-301117
dt17-Nov-17
BUDHIL
BUDHIL
-UPCL
21-Nov-17 30-Nov-17 1600-1900: 60 MW ----
4Nov-17/AP-45403-FS
17-Nov-17
APPCPL/103/2432
dt16-Nov-17
APPCPL
HPPC
-NPCL(UP)
21-Nov-17 30-Nov-17 0000-0700: 11 MW
1700-2400: 11 MW
----
5Nov-17/AP-45413-SD
17-Nov-17
SHEPL/NOV/18
dt17-Nov-17
SHEPL_HP
SHEPL_HP
-TPDDL
18-Nov-17 18-Nov-17 0000-0700: 1.7 MW
0700-1000: 1.65 MW
1000-1300: 1.55 MW
1300-1500: 1.75 MW
1500-1800: 2.02 MW
1800-2200: 1.85 MW
2200-2400: 1.7 MW
----
6Nov-17/AP-45412-SD
17-Nov-17
NHPPL/NOV/18
dt17-Nov-17
NHPPL
NHPPL
-TPDDL
18-Nov-17 18-Nov-17 0000-0300: 2.1 MW
0300-0500: 2.03 MW
0500-0800: 1.95 MW
0800-1200: 1.91 MW
1200-1400: 2.03 MW
1400-1600: 2.1 MW
1600-1800: 2.2 MW
1800-2000: 2.1 MW
2000-2400: 2.03 MW
----
7Nov-17/AP-45411-SD
17-Nov-17
PTC/OA/27830
dt17-Nov-17
PTC
SPDC-JK
-HPPC
18-Nov-17 18-Nov-17 0000-2400: 24.05 MW ----
8Nov-17/AP-45410-DA
17-Nov-17
APPCPL/103/2455
dt17-Nov-17
APPCPL
HPPC
-NPCL(UP)
18-Nov-17 18-Nov-17 0000-1000: 10 MW
1000-1300: 18 MW
1300-1400: 39 MW
1400-1500: 23 MW
1500-1600: 18 MW
1600-1700: 15 MW
1700-1800: 8 MW
1800-1900: 20 MW
1900-2000: 40 MW
2000-2100: 35 MW
2100-2200: 19 MW
2200-2400: 10 MW
----
9Nov-17/AP-45402-FS
17-Nov-17
APPCPL/107/2357/7
dt16-Nov-17
APPCPL
DOPGON
-AHCSPL
20-Nov-17 30-Nov-17 0000-0800: .9 MW
0800-2000: 1.1 MW
2000-2400: .9 MW
NER-ER-NR
10Nov-17/AP-45401-FS
17-Nov-17
APPCPL/107/2357/6
dt16-Nov-17
APPCPL
DOPGON
-WHPL
20-Nov-17 30-Nov-17 0000-2400: .4 MW NER-ER-NR
11Nov-17/AP-45409-DA
17-Nov-17
APPCPL/103/2454
dt17-Nov-17
APPCPL
HPPC
-NPCL(UP)
18-Nov-17 18-Nov-17 0700-1700: 20 MW ----
12Nov-17/AP-45408-DA
17-Nov-17
UPCL/OA/2017-18/13
dt17-Nov-17
UPCL
PSEB
-UPCL
18-Nov-17 18-Nov-17 0000-2400: 75 MW ----
13Nov-17/AP-45414-DA
17-Nov-17
APPCPL/107/2357/7/1
dt17-Nov-17
APPCPL
DOPGON
-AHCSPL
18-Nov-17 18-Nov-17 0000-0800: .9 MW
0800-2000: 1.1 MW
2000-2400: .9 MW
NER-ER-NR
14Nov-17/AP-45407-DA
17-Nov-17
MPL/17-18/STOA/495
dt17-Nov-17
Manikaran
HPSEB
-HPPC
18-Nov-17 18-Nov-17 1800-1930: 200 MW ----
15Nov-17/AP-45406-DA
17-Nov-17
MPL/17-18/STOA/494
dt17-Nov-17
Manikaran
HPPC
-HPSEB
18-Nov-17 18-Nov-17 0700-1200: 60 MW ----
16Nov-17/AP-45405-DA
17-Nov-17
APPCPL/108/2358/2/4
dt17-Nov-17
APPCPL
Sikkim
-ISIC
18-Nov-17 18-Nov-17 0000-2400: .3 MW ER-NR
17Nov-17/AP-45399-SD
16-Nov-17
PTC/OA/27829
dt16-Nov-17
PTC
SPDC-JK
-HPPC
17-Nov-17 17-Nov-17 0000-2400: 16.4 MW ----
18Nov-17/AP-45398-SD
16-Nov-17
APPCPL/103/2451
dt16-Nov-17
APPCPL
HPPC
-NPCL(UP)
17-Nov-17 17-Nov-17 0000-1000: 10 MW
1000-1100: 29 MW
1100-1300: 23 MW
1300-1400: 39 MW
1400-1500: 23 MW
1500-1600: 18 MW
1600-1700: 10 MW
1700-1800: 13 MW
1800-1900: 20 MW
1900-2100: 35 MW
2100-2200: 19 MW
2200-2400: 10 MW
----
19Nov-17/AP-45397-SD
16-Nov-17
UPCL/OA/2017-18/12
dt16-Nov-17
UPCL
PSEB
-UPCL
17-Nov-17 17-Nov-17 0000-2400: 150 MW ----
20Nov-17/AP-45396-DA
16-Nov-17
APPCPL/103/2450
dt16-Nov-17
APPCPL
HPPC
-NPCL(UP)
17-Nov-17 17-Nov-17 0700-1700: 20 MW ----
21Nov-17/AP-45395-DA
16-Nov-17
SHEPL/NOV/17
dt16-Nov-17
SHEPL_HP
SHEPL_HP
-TPDDL
17-Nov-17 17-Nov-17 0000-0700: 1.65 MW
0700-1300: 1.55 MW
1300-1600: 1.7 MW
1600-2100: 1.9 MW
2100-2300: 1.75 MW
2300-2400: 1.65 MW
----
22Nov-17/AP-45394-DA
16-Nov-17
SPT/OA/4633-DA
dt16-Nov-17
SCL
SCLTPS
-NPCL(UP)
17-Nov-17 17-Nov-17 0000-0100: 26 MW
0100-0200: 21 MW
0200-0400: 16 MW
0400-0500: 10 MW
0500-0600: 21 MW
0600-0700: 42 MW
0700-0900: 36 MW
0900-1000: 42 MW
1000-1600: 50 MW
1600-1700: 47 MW
1700-2200: 50 MW
2200-2300: 48 MW
2300-2400: 37 MW
----
23Nov-17/AP-45393-DA
16-Nov-17
NHPPL/NOV/17
dt16-Nov-17
NHPPL
NHPPL
-TPDDL
17-Nov-17 17-Nov-17 0000-0400: 2.1 MW
0400-0800: 2.03 MW
0800-1200: 1.95 MW
1200-1400: 2.06 MW
1400-1600: 2.18 MW
1600-1800: 2.41 MW
1800-2000: 2.33 MW
2000-2400: 2.18 MW
----
24Nov-17/AP-45400-DA
16-Nov-17
APPCPL/108/2358/2/3
dt16-Nov-17
APPCPL
Sikkim
-ISIC
17-Nov-17 17-Nov-17 0000-2400: .3 MW ER-NR
25Nov-17/AP-45392-FS
16-Nov-17
APPCPL/108/2358/2
dt15-Nov-17
APPCPL
Sikkim
-ISIC
19-Nov-17 30-Nov-17 0000-2400: .3 MW ER-NR
26Nov-17/AP-45390-SD
15-Nov-17
PTC/OA/27828
dt15-Nov-17
PTC
SPDC-JK
-HPPC
16-Nov-17 16-Nov-17 0000-2400: 16.4 MW ----
27Nov-17/AP-45389-SD
15-Nov-17
SPT/OA/4632-DA
dt15-Nov-17
SCL
SCLTPS
-NPCL(UP)
16-Nov-17 16-Nov-17 0000-0100: 21 MW
0100-0200: 16 MW
0200-0400: 10 MW
0400-0500: 5 MW
0500-0600: 21 MW
0600-0700: 42 MW
0700-0800: 31 MW
0800-0900: 26 MW
0900-1000: 36 MW
1000-1400: 50 MW
1400-1500: 45 MW
1500-1600: 50 MW
1600-1700: 47 MW
1700-2200: 50 MW
2200-2300: 43 MW
2300-2400: 32 MW
----
28Nov-17/AP-45388-SD
15-Nov-17
UPCL/OA/2017-18/11
dt15-Nov-17
UPCL
PSEB
-UPCL
16-Nov-17 16-Nov-17 0000-2400: 100 MW ----
29Nov-17/AP-45387-DA
15-Nov-17
APPCPL/103/2440
dt15-Nov-17
APPCPL
HPPC
-NPCL(UP)
16-Nov-17 16-Nov-17 0000-1000: 10 MW
1000-1500: 18 MW
1500-1600: 12 MW
1600-1700: 10 MW
1700-1800: 13 MW
1800-2000: 29 MW
2000-2100: 24 MW
2100-2200: 13 MW
2200-2400: 10 MW
----
30Nov-17/AP-45386-DA
15-Nov-17
APPCPL/103/2439
dt15-Nov-17
APPCPL
HPPC
-NPCL(UP)
16-Nov-17 16-Nov-17 0700-1700: 20 MW ----
31Nov-17/AP-45385-DA
15-Nov-17
GBHPL/UPCL/16112017
dt15-Nov-17
BUDHIL
BUDHIL
-UPCL
16-Nov-17 16-Nov-17 0900-1300: 60 MW ----
32Nov-17/AP-45384-DA
15-Nov-17
NHPPL/NOV/16
dt15-Nov-17
NHPPL
NHPPL
-TPDDL
16-Nov-17 16-Nov-17 0000-0400: 2.1 MW
0400-0800: 2.03 MW
0800-1000: 1.97 MW
1000-1300: 2.05 MW
1300-1600: 2.22 MW
1600-1800: 2.29 MW
1800-2000: 2.48 MW
2000-2400: 2.33 MW
----
33Nov-17/AP-45383-DA
15-Nov-17
SHEPL/NOV/16
dt15-Nov-17
SHEPL_HP
SHEPL_HP
-TPDDL
16-Nov-17 16-Nov-17 0000-0700: 1.79 MW
0700-1000: 1.71 MW
1000-1500: 1.75 MW
1500-2000: 2.06 MW
2000-2300: 1.9 MW
2300-2400: 1.75 MW
----
34Nov-17/AP-45391-DA
15-Nov-17
APPCPL/108/2358/2/2
dt15-Nov-17
APPCPL
Sikkim
-ISIC
16-Nov-17 16-Nov-17 0000-2400: .3 MW ER-NR
35Nov-17/AP-45381-SD
14-Nov-17
PTC/OA/27827
dt14-Nov-17
PTC
SPDC-JK
-HPPC
15-Nov-17 15-Nov-17 0000-2400: 16.4 MW ----
36Nov-17/AP-45382-SD
14-Nov-17
MPL/17-18/STOA/485
dt14-Nov-17
Manikaran
MPPMCL
-HPPC
15-Nov-17 15-Nov-17 0000-1200: 0 MW
1200-1300: 200 MW
1300-1400: 250 MW
1400-1430: 200 MW
1430-2400: 0 MW
WR-NR
37Nov-17/AP-45380-DA
14-Nov-17
UPCL/OA/2017-18/10
dt14-Nov-17
UPCL
PSEB
-UPCL
15-Nov-17 15-Nov-17 0000-0200: 150 MW
0200-0400: 100 MW
0400-0700: 150 MW
0700-1900: 50 MW
1900-2000: 100 MW
2000-2200: 50 MW
2200-2400: 150 MW
----
38Nov-17/AP-45379-DA
14-Nov-17
APPCPL/103/2438
dt14-Nov-17
APPCPL
HPPC
-NPCL(UP)
15-Nov-17 15-Nov-17 0000-1000: 10 MW
1000-1200: 18 MW
1200-1300: 23 MW
1300-1400: 34 MW
1400-1500: 18 MW
1500-1600: 12 MW
1600-1700: 10 MW
1700-1800: 13 MW
1800-1900: 29 MW
1900-2100: 24 MW
2100-2200: 13 MW
2200-2400: 10 MW
----
39Nov-17/AP-45378-DA
14-Nov-17
SHEPL/NOV/15
dt14-Nov-17
SHEPL_HP
SHEPL_HP
-TPDDL
15-Nov-17 15-Nov-17 0000-0900: 1.9 MW
0900-1400: 1.85 MW
1400-1700: 2 MW
1700-2300: 2.05 MW
2300-2400: 1.85 MW
----
40Nov-17/AP-45377-DA
14-Nov-17
APPCPL/103/2437
dt14-Nov-17
APPCPL
HPPC
-NPCL(UP)
15-Nov-17 15-Nov-17 0700-1700: 20 MW ----
41Nov-17/AP-45376-DA
14-Nov-17
SPT/OA/4631-DA
dt14-Nov-17
SCL
SCLTPS
-NPCL(UP)
15-Nov-17 15-Nov-17 0000-0100: 21 MW
0100-0200: 16 MW
0200-0400: 10 MW
0400-0500: 5 MW
0500-0600: 21 MW
0600-0700: 42 MW
0700-0900: 26 MW
0900-1000: 42 MW
1000-1600: 50 MW
1600-1700: 47 MW
1700-2200: 50 MW
2200-2300: 43 MW
2300-2400: 32 MW
----
42Nov-17/AP-45375-DA
14-Nov-17
NHPPL/NOV/15
dt14-Nov-17
NHPPL
NHPPL
-TPDDL
15-Nov-17 15-Nov-17 0000-0400: 2.33 MW
0400-0800: 2.18 MW
0800-1200: 2.29 MW
1200-1600: 2.38 MW
1600-2000: 2.43 MW
2000-2200: 2.41 MW
2200-2400: 2.22 MW
----
43Nov-17/AP-45374-FS
14-Nov-17
GBHPL/UPCL/17-201117
dt13-Nov-17
BUDHIL
BUDHIL
-UPCL
17-Nov-17 20-Nov-17 0900-1300: 60 MW ----
44Nov-17/AP-45372-SD
13-Nov-17
PTC/OA/27817
dt13-Nov-17
PTC
SPDC-JK
-HPPC
14-Nov-17 14-Nov-17 0000-2400: 16.4 MW ----
45Nov-17/AP-45366-SD
13-Nov-17
PSPCL/OA/2017-18/112
dt13-Nov-17
PSEB
MPPMCL
-PSEB
13-Nov-17 13-Nov-17 0000-2000: 0 MW
2000-2200: 200 MW
2200-2400: 0 MW
WR-NR
46Nov-17/AP-45371-DA
13-Nov-17
APPCPL/103/2436
dt13-Nov-17
APPCPL
HPPC
-NPCL(UP)
14-Nov-17 14-Nov-17 0700-1700: 20 MW ----
47Nov-17/AP-45370-DA
13-Nov-17
APPCPL/103/2435
dt13-Nov-17
APPCPL
HPPC
-NPCL(UP)
14-Nov-17 14-Nov-17 0000-0600: 20 MW
0600-0700: 23 MW
0700-0900: 10 MW
0900-1000: 12 MW
1000-1200: 29 MW
1200-1300: 39 MW
1300-1400: 45 MW
1400-1500: 39 MW
1500-1700: 29 MW
1700-1800: 35 MW
1800-1900: 30 MW
1900-2000: 50 MW
2000-2100: 45 MW
2100-2200: 29 MW
2200-2300: 13 MW
2300-2400: 10 MW
----
48Nov-17/AP-45369-DA
13-Nov-17
SPT/OA/4625-DA
dt13-Nov-17
SCL
SCLTPS
-NPCL(UP)
14-Nov-17 14-Nov-17 0000-0100: 27 MW
0100-0400: 22 MW
0400-0500: 16 MW
0500-0600: 27 MW
0600-0700: 40 MW
0700-0800: 36 MW
0800-0900: 42 MW
0900-2300: 50 MW
2300-2400: 43 MW
----
49Nov-17/AP-45368-DA
13-Nov-17
SHEPL/NOV/14
dt13-Nov-17
SHEPL_HP
SHEPL_HP
-TPDDL
14-Nov-17 14-Nov-17 0000-0300: 2.07 MW
0300-1000: 1.92 MW
1000-1400: 1.88 MW
1400-1700: 2.19 MW
1700-2000: 2.15 MW
2000-2200: 2.35 MW
2200-2400: 2.19 MW
----
50Nov-17/AP-45373-DA
13-Nov-17
MPL/17-18/STOA/482
dt13-Nov-17
Manikaran
MPPMCL
-HPPC
14-Nov-17 14-Nov-17 0000-1200: 0 MW
1200-1300: 300 MW
1300-1445: 200 MW
1445-2400: 0 MW
WR-NR
51Nov-17/AP-45367-DA
13-Nov-17
NHPPL/NOV/14
dt13-Nov-17
NHPPL
NHPPL
-TPDDL
14-Nov-17 14-Nov-17 0000-0400: 2.31 MW
0400-0800: 2.18 MW
0800-1200: 2.33 MW
1200-1600: 2.41 MW
1600-1900: 2.48 MW
1900-2100: 2.63 MW
2100-2400: 2.53 MW
----
52Nov-17/AP-45362-SD
12-Nov-17
PTC/OA/27816
dt12-Nov-17
PTC
SPDC-JK
-HPPC
13-Nov-17 13-Nov-17 0000-1000: 24.05 MW
1000-2400: 16.4 MW
----
53Nov-17/AP-45361-DA
12-Nov-17
NHPPL/NOV/13
dt12-Nov-17
NHPPL
NHPPL
-TPDDL
13-Nov-17 13-Nov-17 0000-0200: 2.48 MW
0200-0400: 2.41 MW
0400-0600: 2.33 MW
0600-1000: 2.16 MW
1000-1200: 2.26 MW
1200-1500: 2.35 MW
1500-1700: 2.41 MW
1700-2000: 2.51 MW
2000-2400: 2.48 MW
----
54Nov-17/AP-45360-DA
12-Nov-17
SHEPL/NOV/13
dt12-Nov-17
SHEPL_HP
SHEPL_HP
-TPDDL
13-Nov-17 13-Nov-17 0000-0100: 2.1 MW
0100-0800: 2.02 MW
0800-0900: 1.94 MW
0900-1400: 1.86 MW
1400-1900: 2.02 MW
1900-2000: 2.41 MW
2000-2400: 2.17 MW
----
55Nov-17/AP-45365-DA
12-Nov-17
MPL/17-18/STOA/480
dt12-Nov-17
Manikaran
MPPMCL
-HPPC
13-Nov-17 13-Nov-17 0000-1215: 0 MW
1215-1315: 300 MW
1315-1415: 150 MW
1415-2400: 0 MW
WR-NR
56Nov-17/AP-45359-DA
12-Nov-17
SPT/OA/4624-DA
dt12-Nov-17
SCL
SCLTPS
-NPCL(UP)
13-Nov-17 13-Nov-17 0000-0100: 4 MW
0500-0600: 10 MW
0600-0700: 4 MW
0700-0900: 25 MW
0900-2300: 50 MW
2300-2400: 41 MW
----
57Nov-17/AP-45358-DA
12-Nov-17
APPCPL/103/2434
dt12-Nov-17
APPCPL
HPPC
-NPCL(UP)
13-Nov-17 13-Nov-17 0000-1000: 10 MW
1000-1100: 27 MW
1100-1300: 33 MW
1300-1400: 43 MW
1400-1500: 38 MW
1500-1600: 33 MW
1600-1700: 27 MW
1700-1800: 17 MW
1800-1900: 20 MW
1900-2000: 49 MW
2000-2100: 44 MW
2100-2200: 28 MW
2200-2300: 12 MW
2300-2400: 10 MW
----
58Nov-17/AP-45357-DA
12-Nov-17
APPCPL/103/2433
dt12-Nov-17
APPCPL
HPPC
-NPCL(UP)
13-Nov-17 13-Nov-17 0700-1700: 20 MW ----
59Nov-17/AP-45364-DA
12-Nov-17
APPCPL/107/2357/5/3
dt12-Nov-17
APPCPL
DOPGON
-MHIL
13-Nov-17 13-Nov-17 0000-2400: .7 MW NER-ER-NR
60Nov-17/AP-45363-DA
12-Nov-17
APPCPL/108/2358/1/3
dt12-Nov-17
APPCPL
Sikkim
-RGCIRC
13-Nov-17 13-Nov-17 0000-2400: .8 MW ER-NR
61Nov-17/AP-45354-SD
11-Nov-17
PTC/OA/27811
dt11-Nov-17
PTC
SPDC-JK
-HPPC
12-Nov-17 12-Nov-17 0000-1000: 16.49 MW
1000-2400: 24.19 MW
----
62Nov-17/AP-45353-DA
11-Nov-17
APPCPL/103/2431
dt11-Nov-17
APPCPL
HPPC
-NPCL(UP)
12-Nov-17 12-Nov-17 0700-1700: 20 MW ----
63Nov-17/AP-45352-DA
11-Nov-17
SPT/OA/4623-DA
dt11-Nov-17
SCL
SCLTPS
-NPCL(UP)
12-Nov-17 12-Nov-17 0000-0100: 46 MW
0100-0300: 41 MW
0300-0400: 35 MW
0400-0500: 30 MW
0500-0600: 35 MW
0600-0700: 46 MW
0700-0800: 13 MW
0800-0900: 3 MW
0900-1000: 8 MW
1000-1100: 19 MW
1100-1200: 29 MW
1200-1300: 35 MW
1300-1400: 29 MW
1400-1500: 24 MW
1500-1700: 13 MW
1700-1800: 3 MW
1800-2000: 46 MW
2000-2100: 41 MW
2100-2200: 30 MW
2200-2300: 25 MW
2300-2400: 19 MW
----
64Nov-17/AP-45351-DA
11-Nov-17
NHPPL/NOV/12
dt11-Nov-17
NHPPL
NHPPL
-TPDDL
12-Nov-17 12-Nov-17 0000-0300: 2.5 MW
0300-0500: 2.4 MW
0500-0900: 2.35 MW
0900-1200: 2.5 MW
1200-1400: 2.55 MW
1400-1700: 2.65 MW
1700-2000: 2.7 MW
2000-2400: 2.55 MW
----
65Nov-17/AP-45350-DA
11-Nov-17
SHEPL/NOV/12
dt11-Nov-17
SHEPL_HP
SHEPL_HP
-TPDDL
12-Nov-17 12-Nov-17 0000-0800: 2.27 MW
0800-0900: 2.34 MW
0900-1600: 2.27 MW
1600-2200: 2.42 MW
2200-2400: 2.23 MW
----
66Nov-17/AP-45356-DA
11-Nov-17
APPCPL/107/2357/5/2
dt11-Nov-17
APPCPL
DOPGON
-MHIL
12-Nov-17 12-Nov-17 0000-2400: .7 MW NER-ER-NR
67Nov-17/AP-45355-DA
11-Nov-17
APPCPL/108/2358/1/2
dt11-Nov-17
APPCPL
Sikkim
-RGCIRC
12-Nov-17 12-Nov-17 0000-2400: .8 MW ER-NR
68Nov-17/AP-45340-FS
10-Nov-17
APPCPL/107/2357/5
dt10-Nov-17
APPCPL
DOPGON
-MHIL
14-Nov-17 30-Nov-17 0000-2400: .7 MW NER-ER-NR
69Nov-17/AP-45339-FS
10-Nov-17
APPCPL/108/2358/1
dt10-Nov-17
APPCPL
Sikkim
-RGCIRC
14-Nov-17 30-Nov-17 0000-2400: .8 MW ER-NR
70Nov-17/AP-45346-SD
10-Nov-17
PTC/OA/27810
dt10-Nov-17
PTC
SPDC-JK
-HPPC
11-Nov-17 11-Nov-17 0000-2400: 16.49 MW ----
71Nov-17/AP-45345-SD
10-Nov-17
SPT/OA/4622-DA
dt10-Nov-17
SCL
SCLTPS
-NPCL(UP)
11-Nov-17 11-Nov-17 0000-0100: 36 MW
0100-0300: 31 MW
0300-0500: 25 MW
0500-0600: 36 MW
0600-0700: 50 MW
0700-0900: 41 MW
0900-1200: 45 MW
1200-2300: 50 MW
2300-2400: 41 MW
----
72Nov-17/AP-45344-DA
10-Nov-17
APPCPL/103/2430
dt10-Nov-17
APPCPL
HPPC
-NPCL(UP)
11-Nov-17 11-Nov-17 0700-1700: 20 MW ----
73Nov-17/AP-45343-DA
10-Nov-17
APPCPL/103/2429
dt10-Nov-17
APPCPL
HPPC
-NPCL(UP)
11-Nov-17 11-Nov-17 0000-0900: 10 MW
0900-1000: 11 MW
1000-1100: 22 MW
1100-1200: 27 MW
1200-1400: 33 MW
1400-1600: 22 MW
1600-1700: 17 MW
1700-1800: 12 MW
1800-1900: 20 MW
1900-2000: 44 MW
2000-2100: 34 MW
2100-2200: 23 MW
2200-2300: 12 MW
2300-2400: 10 MW
----
74Nov-17/AP-45349-DA
10-Nov-17
MPL/17-18/STOA/473
dt10-Nov-17
Manikaran
MPPMCL
-HPPC
11-Nov-17 11-Nov-17 0000-1215: 0 MW
1215-1300: 300 MW
1300-1345: 200 MW
1345-2400: 0 MW
WR-NR
75Nov-17/AP-45348-DA
10-Nov-17
APPCPL/107/2357/5/1
dt10-Nov-17
APPCPL
DOPGON
-MHIL
11-Nov-17 11-Nov-17 0000-2400: .7 MW NER-ER-NR
76Nov-17/AP-45342-DA
10-Nov-17
NHPPL/NOV/11
dt10-Nov-17
NHPPL
NHPPL
-TPDDL
11-Nov-17 11-Nov-17 0000-0500: 2.62 MW
0500-0700: 2.54 MW
0700-1100: 2.47 MW
1100-1700: 2.62 MW
1700-1900: 2.66 MW
1900-2200: 2.64 MW
2200-2400: 2.5 MW
----
77Nov-17/AP-45347-DA
10-Nov-17
APPCPL/108/2358/1/1
dt10-Nov-17
APPCPL
Sikkim
-RGCIRC
11-Nov-17 11-Nov-17 0000-2400: .8 MW ER-NR
78Nov-17/AP-45341-DA
10-Nov-17
SHEPL/NOV/11
dt10-Nov-17
SHEPL_HP
SHEPL_HP
-TPDDL
11-Nov-17 11-Nov-17 0000-0200: 2.27 MW
0200-0900: 2.34 MW
0900-1600: 2.4 MW
1600-2300: 2.42 MW
2300-2400: 2.23 MW
----
79Nov-17/AP-45338-SD
09-Nov-17
MPL/17-18/STOA/471
dt09-Nov-17
Manikaran
MPPMCL
-HPPC
10-Nov-17 10-Nov-17 0000-1130: 0 MW
1130-1430: 200 MW
1430-2400: 0 MW
WR-NR
80Nov-17/AP-45337-SD
09-Nov-17
PTC/OA/27809
dt09-Nov-17
PTC
SPDC-JK
-HPPC
10-Nov-17 10-Nov-17 0000-2400: 16.49 MW ----
81Nov-17/AP-45336-SD
09-Nov-17
APPCPL/103/2423
dt09-Nov-17
APPCPL
HPPC
-NPCL(UP)
10-Nov-17 10-Nov-17 0000-0900: 10 MW
0900-1000: 11 MW
1000-1100: 17 MW
1100-1300: 22 MW
1300-1400: 33 MW
1400-1500: 27 MW
1500-1800: 17 MW
1800-1900: 20 MW
1900-2000: 50 MW
2000-2100: 44 MW
2100-2200: 28 MW
2200-2300: 12 MW
2300-2400: 10 MW
----
82Nov-17/AP-45335-SD
09-Nov-17
APPCPL/103/2422
dt09-Nov-17
APPCPL
HPPC
-NPCL(UP)
10-Nov-17 10-Nov-17 0700-1700: 20 MW ----
83Nov-17/AP-45334-SD
09-Nov-17
SPT/OA/4621-DA
dt09-Nov-17
SCL
SCLTPS
-NPCL(UP)
10-Nov-17 10-Nov-17 0000-0100: 36 MW
0100-0400: 31 MW
0400-0500: 25 MW
0500-0600: 36 MW
0600-0700: 50 MW
0700-0800: 35 MW
0800-0900: 41 MW
0900-1000: 40 MW
1000-2300: 50 MW
2300-2400: 41 MW
----
84Nov-17/AP-45333-DA
09-Nov-17
07-BYPL/Nov-17(DA)
dt09-Nov-17
HPSEB
BYPL
-HPSEB
10-Nov-17 10-Nov-17 0700-0900: 35 MW
0900-1000: 20 MW
----
85Nov-17/AP-45332-DA
09-Nov-17
BYPL/HP/Nov-17/DA-25
dt09-Nov-17
BYPL
HPSEB
-BYPL
10-Nov-17 10-Nov-17 1745-1945: 40 MW ----
86Nov-17/AP-45331-DA
09-Nov-17
UPCL/OA/2017-18/09
dt09-Nov-17
UPCL
PSEB
-UPCL
10-Nov-17 10-Nov-17 0000-0600: 100 MW
1500-2100: 50 MW
2100-2400: 100 MW
----
87Nov-17/AP-45330-DA
09-Nov-17
NHPPL/NOV/10
dt09-Nov-17
NHPPL
NHPPL
-TPDDL
10-Nov-17 10-Nov-17 0000-0400: 2.65 MW
0400-0800: 2.55 MW
0800-1100: 2.5 MW
1100-1400: 2.55 MW
1400-1700: 2.65 MW
1700-2200: 2.74 MW
2200-2400: 2.65 MW
----
88Nov-17/AP-45329-DA
09-Nov-17
SHEPL/NOV/10
dt09-Nov-17
SHEPL_HP
SHEPL_HP
-TPDDL
10-Nov-17 10-Nov-17 0000-0300: 2.4 MW
0300-0800: 2.35 MW
0800-1000: 2.3 MW
1000-1200: 2.27 MW
1200-2300: 2.4 MW
2300-2400: 2.27 MW
----
89Nov-17/AP-45327-SD
08-Nov-17
PTC/OA/27808
dt08-Nov-17
PTC
SPDC-JK
-HPPC
09-Nov-17 09-Nov-17 0000-2400: 24.19 MW ----
90Nov-17/AP-45326-DA
08-Nov-17
APPCPL/103/2421
dt08-Nov-17
APPCPL
HPPC
-NPCL(UP)
09-Nov-17 09-Nov-17 0000-0900: 10 MW
0900-1000: 16 MW
1000-1100: 27 MW
1100-1200: 32 MW
1200-1500: 37 MW
1500-1600: 32 MW
1600-1700: 27 MW
1700-1800: 17 MW
1800-1900: 20 MW
1900-2000: 50 MW
2000-2100: 39 MW
2100-2200: 28 MW
2200-2300: 12 MW
2300-2400: 10 MW
----
91Nov-17/AP-45325-DA
08-Nov-17
APPCPL/103/2420
dt08-Nov-17
APPCPL
HPPC
-NPCL(UP)
09-Nov-17 09-Nov-17 0700-1700: 20 MW ----
92Nov-17/AP-45324-DA
08-Nov-17
06-BYPL/Nov-17(DA)
dt08-Nov-17
HPSEB
BYPL
-HPSEB
09-Nov-17 09-Nov-17 0700-0900: 30 MW
0900-1000: 20 MW
----
93Nov-17/AP-45323-DA
08-Nov-17
BYPL/HP/Nov-17/DA-24
dt08-Nov-17
BYPL
HPSEB
-BYPL
09-Nov-17 09-Nov-17 1800-2000: 40 MW ----
94Nov-17/AP-45322-DA
08-Nov-17
SPT/OA/4620-DA
dt08-Nov-17
SCL
SCLTPS
-NPCL(UP)
09-Nov-17 09-Nov-17 0000-0100: 36 MW
0100-0300: 31 MW
0300-0500: 25 MW
0500-0600: 36 MW
0600-0700: 47 MW
0700-0900: 41 MW
0900-1700: 40 MW
1700-2300: 50 MW
2300-2400: 41 MW
----
95Nov-17/AP-45328-DA
08-Nov-17
MPL/17-18/STOA/464
dt08-Nov-17
Manikaran
MPPMCL
-HPPC
09-Nov-17 09-Nov-17 0000-1200: 0 MW
1200-1430: 240 MW
1430-2400: 0 MW
WR-NR
96Nov-17/AP-45321-DA
08-Nov-17
NHPPL/NOV/09
dt08-Nov-17
NHPPL
NHPPL
-TPDDL
09-Nov-17 09-Nov-17 0000-0300: 2.77 MW
0300-0500: 2.7 MW
0500-1200: 2.62 MW
1200-1600: 2.7 MW
1600-2000: 2.77 MW
2000-2400: 2.85 MW
----
97Nov-17/AP-45320-DA
08-Nov-17
SHEPL/NOV/09
dt08-Nov-17
SHEPL_HP
SHEPL_HP
-TPDDL
09-Nov-17 09-Nov-17 0000-0600: 2.45 MW
0600-0800: 2.35 MW
0800-1000: 2.45 MW
1000-1800: 2.48 MW
1800-2200: 2.52 MW
2200-2400: 2.45 MW
----
98Nov-17/AP-45319-FS
08-Nov-17
GBHPL/UPCL/11-201117
dt07-Nov-17
BUDHIL
BUDHIL
-UPCL
11-Nov-17 15-Nov-17 1000-1500: 60 MW ----
99Nov-17/AP-45318-FS
08-Nov-17
PTC/OA/27803
dt06-Nov-17
PTC
SCLTPS
-NEPAL
11-Nov-17 30-Nov-17 0000-2400: 30 MW ----
100Nov-17/AP-45316-DA
07-Nov-17
PTC/OA/27807
dt07-Nov-17
PTC
SPDC-JK
-HPPC
08-Nov-17 08-Nov-17 0000-2400: 24.19 MW ----
101Nov-17/AP-45315-DA
07-Nov-17
SPT/OA/4619-DA
dt07-Nov-17
SCL
SCLTPS
-NPCL(UP)
08-Nov-17 08-Nov-17 0000-0100: 36 MW
0100-0200: 31 MW
0200-0500: 25 MW
0500-0600: 36 MW
0600-0700: 47 MW
0700-0800: 46 MW
0800-0900: 41 MW
0900-2300: 50 MW
2300-2400: 41 MW
----
102Nov-17/AP-45314-DA
07-Nov-17
APPCPL/103/2406
dt07-Nov-17
APPCPL
HPPC
-NPCL(UP)
08-Nov-17 08-Nov-17 0000-0900: 10 MW
0900-1000: 11 MW
1000-1100: 27 MW
1100-1200: 33 MW
1200-1400: 38 MW
1400-1500: 43 MW
1500-1700: 33 MW
1700-1800: 17 MW
1800-1900: 20 MW
1900-2000: 50 MW
2000-2100: 44 MW
2100-2200: 28 MW
2200-2300: 12 MW
2300-2400: 10 MW
----
103Nov-17/AP-45313-DA
07-Nov-17
APPCPL/103/2405
dt07-Nov-17
APPCPL
HPPC
-NPCL(UP)
08-Nov-17 08-Nov-17 0700-1700: 10 MW ----
104Nov-17/AP-45317-DA
07-Nov-17
MPL/17-18/STOA/462
dt07-Nov-17
Manikaran
MPPMCL
-HPPC
08-Nov-17 08-Nov-17 0000-1200: 0 MW
1200-1430: 240 MW
1430-2400: 0 MW
WR-NR
105Nov-17/AP-45312-DA
07-Nov-17
05-BYPL/Nov-17(DA)
dt07-Nov-17
HPSEB
BYPL
-HPSEB
08-Nov-17 08-Nov-17 0700-1000: 35 MW ----
106Nov-17/AP-45311-DA
07-Nov-17
BYPL/HP/Nov-17/DA-23
dt07-Nov-17
BYPL
HPSEB
-BYPL
08-Nov-17 08-Nov-17 1700-1800: 25 MW
1800-1900: 45 MW
1900-2000: 25 MW
----
107Nov-17/AP-45310-DA
07-Nov-17
SHEPL/NOV/08
dt07-Nov-17
SHEPL_HP
SHEPL_HP
-TPDDL
08-Nov-17 08-Nov-17 0000-0100: 2.48 MW
0100-0600: 2.46 MW
0600-0900: 2.48 MW
0900-1400: 2.46 MW
1400-1700: 2.48 MW
1700-2300: 2.54 MW
2300-2400: 2.49 MW
----
108Nov-17/AP-45309-DA
07-Nov-17
NHPPL/NOV/08
dt07-Nov-17
NHPPL
NHPPL
-TPDDL
08-Nov-17 08-Nov-17 0000-0300: 2.8 MW
0300-0600: 2.75 MW
0600-1000: 2.65 MW
1000-1500: 2.75 MW
1500-1600: 2.8 MW
1600-2000: 2.9 MW
2000-2400: 2.8 MW
----
109Nov-17/AP-45307-SD
06-Nov-17
PTC/OA/27806
dt06-Nov-17
PTC
SPDC-JK
-HPPC
07-Nov-17 07-Nov-17 0000-2400: 24.19 MW ----
110Nov-17/AP-45306-SD
06-Nov-17
04-BYPL/Nov-17(DA)
dt06-Nov-17
HPSEB
BYPL
-HPSEB
07-Nov-17 07-Nov-17 0700-1000: 30 MW ----
111Nov-17/AP-45305-SD
06-Nov-17
BYPL/HP/Nov-17/DA-22
dt06-Nov-17
BYPL
HPSEB
-BYPL
07-Nov-17 07-Nov-17 1800-2000: 45 MW ----
112Nov-17/AP-45304-SD
06-Nov-17
UPCL/OA/2017-18/08
dt06-Nov-17
UPCL
PSEB
-UPCL
07-Nov-17 07-Nov-17 1300-1500: 100 MW
2200-2400: 100 MW
----
113Nov-17/AP-45303-DA
06-Nov-17
NPCL/APPCPL/071117
dt06-Nov-17
NPCL(UP)
HPPC
-NPCL(UP)
07-Nov-17 07-Nov-17 0000-0600: 10 MW
0600-0700: 12 MW
0700-0900: 10 MW
0900-1000: 17 MW
1000-1200: 33 MW
1200-1500: 43 MW
1500-1600: 38 MW
1600-1700: 33 MW
1700-1800: 23 MW
1800-1900: 20 MW
1900-2000: 55 MW
2000-2100: 44 MW
2100-2200: 34 MW
2200-2300: 23 MW
2300-2400: 12 MW
----
114Nov-17/AP-45302-DA
06-Nov-17
NHPPL/NOV/07
dt06-Nov-17
NHPPL
NHPPL
-TPDDL
07-Nov-17 07-Nov-17 0000-0300: 2.8 MW
0300-0600: 2.74 MW
0600-1000: 2.65 MW
1000-1600: 2.74 MW
1600-2200: 2.8 MW
2200-2400: 2.74 MW
----
115Nov-17/AP-45308-DA
06-Nov-17
MPL/17-18/STOA/456
dt06-Nov-17
Manikaran
MPPMCL
-HPPC
07-Nov-17 07-Nov-17 0000-1200: 0 MW
1200-1500: 200 MW
1500-2400: 0 MW
WR-NR
116Nov-17/AP-45301-DA
06-Nov-17
APPCPL/103/2404
dt06-Nov-17
APPCPL
HPPC
-NPCL(UP)
07-Nov-17 07-Nov-17 0700-1700: 20 MW ----
117Nov-17/AP-45300-DA
06-Nov-17
SPT/OA/4618-DA
dt06-Nov-17
SCL
SCLTPS
-NPCL(UP)
07-Nov-17 07-Nov-17 0000-0100: 36 MW
0100-0400: 31 MW
0400-0500: 25 MW
0500-0600: 36 MW
0600-0700: 45 MW
0700-0900: 35 MW
0900-1800: 45 MW
1800-1900: 50 MW
1900-2400: 45 MW
----
118Nov-17/AP-45299-DA
06-Nov-17
SHEPL/NOV/07
dt06-Nov-17
SHEPL_HP
SHEPL_HP
-TPDDL
07-Nov-17 07-Nov-17 0000-0300: 2.46 MW
0300-0800: 2.42 MW
0800-0900: 2.46 MW
0900-1600: 2.42 MW
1600-2400: 2.46 MW
----
119Nov-17/AP-45298-SD
05-Nov-17
NPCL/APPCPL/061117
dt05-Nov-17
NPCL(UP)
HPPC
-NPCL(UP)
06-Nov-17 06-Nov-17 0000-0500: 10 MW
0500-0600: 5 MW
0600-0700: 17 MW
0700-0900: 10 MW
0900-1000: 16 MW
1000-1100: 32 MW
1100-1200: 38 MW
1200-1600: 43 MW
1600-1700: 32 MW
1700-1800: 12 MW
1800-1900: 20 MW
1900-2000: 54 MW
2000-2100: 43 MW
2100-2200: 33 MW
2200-2300: 22 MW
2300-2400: 12 MW
----
120Nov-17/AP-45297-SD
05-Nov-17
SPT/OA/4617-DA
dt05-Nov-17
SCL
SCLTPS
-NPCL(UP)
06-Nov-17 06-Nov-17 0000-0100: 25 MW
0100-0300: 20 MW
0300-0400: 14 MW
0400-0500: 9 MW
0500-0600: 5 MW
0600-0700: 50 MW
0700-0800: 30 MW
0800-0900: 35 MW
0900-2400: 50 MW
----
121Nov-17/AP-45296-SD
05-Nov-17
03-BYPL/Nov-17(DA)
dt05-Nov-17
HPSEB
BYPL
-HPSEB
06-Nov-17 06-Nov-17 0700-0900: 40 MW ----
122Nov-17/AP-45295-SD
05-Nov-17
PTC/OA/27805
dt05-Nov-17
PTC
SPDC-JK
-HPPC
06-Nov-17 06-Nov-17 0000-2400: 24.19 MW ----
123Nov-17/AP-45294-SD
05-Nov-17
BYPL/HP/Nov-17/DA-21
dt05-Nov-17
BYPL
HPSEB
-BYPL
06-Nov-17 06-Nov-17 1745-1945: 40 MW ----
124Nov-17/AP-45293-SD
05-Nov-17
UPCL/OA/2017-18/07
dt05-Nov-17
UPCL
PSEB
-UPCL
06-Nov-17 06-Nov-17 1230-1500: 100 MW
2200-2400: 100 MW
----
125Nov-17/AP-45292-DA
05-Nov-17
SHEPL/NOV/06
dt05-Nov-17
SHEPL_HP
SHEPL_HP
-TPDDL
06-Nov-17 06-Nov-17 0000-2400: 2.45 MW ----
126Nov-17/AP-45291-DA
05-Nov-17
APPCPL/103/2403
dt05-Nov-17
APPCPL
HPPC
-NPCL(UP)
06-Nov-17 06-Nov-17 0700-1700: 20 MW ----
127Nov-17/AP-45290-DA
05-Nov-17
NHPPL/NOV/06
dt05-Nov-17
NHPPL
NHPPL
-TPDDL
06-Nov-17 06-Nov-17 0000-0800: 2.75 MW
0800-1200: 2.65 MW
1200-1600: 2.75 MW
1600-1800: 2.8 MW
1800-2000: 2.75 MW
2000-2200: 2.8 MW
2200-2400: 2.75 MW
----
128Nov-17/AP-45289-SD
04-Nov-17
709412
dt04-Nov-17
ADANI
APL-Stage1
-RPPC
05-Nov-17 05-Nov-17 0000-1000: 100 MW
1000-1300: 0 MW
1300-2400: 100 MW
WR-ER-NR
129Nov-17/AP-45287-SD
04-Nov-17
PTC/OA/27804
dt04-Nov-17
PTC
SPDC-JK
-HPPC
05-Nov-17 05-Nov-17 0000-2400: 24.01 MW ----
130Nov-17/AP-45288-SD
04-Nov-17
709411
dt04-Nov-17
ADANI
APL-Stage3
-RPPC
05-Nov-17 05-Nov-17 0000-2400: 245 MW WR-ER-NR
131Nov-17/AP-45286-SD
04-Nov-17
SPT/OA/4616-DA
dt04-Nov-17
SCL
SCLTPS
-NPCL(UP)
05-Nov-17 05-Nov-17 0000-0100: 46 MW
0100-0500: 36 MW
0500-0600: 41 MW
0600-0700: 50 MW
0700-0800: 29 MW
0800-0900: 18 MW
0900-1000: 24 MW
1000-1200: 34 MW
1200-1300: 40 MW
1300-1400: 45 MW
1400-1500: 40 MW
1500-1600: 29 MW
1600-1700: 24 MW
1700-1800: 8 MW
1800-2100: 50 MW
2100-2200: 46 MW
2200-2300: 41 MW
2300-2400: 30 MW
----
132Nov-17/AP-45285-SD
04-Nov-17
UPCL/OA/2017-18/06
dt04-Nov-17
UPCL
PSEB
-UPCL
05-Nov-17 05-Nov-17 0000-0600: 50 MW
0900-1100: 50 MW
1100-1300: 100 MW
2200-2400: 100 MW
----
133Nov-17/AP-45284-SD
04-Nov-17
BYPL/HP/Nov-17/DA-20
dt04-Nov-17
BYPL
HPSEB
-BYPL
05-Nov-17 05-Nov-17 1730-1800: 20 MW
1800-1900: 50 MW
1900-2000: 40 MW
----
134Nov-17/AP-45283-DA
04-Nov-17
APPCPL/103/2401
dt04-Nov-17
APPCPL
HPPC
-NPCL(UP)
05-Nov-17 05-Nov-17 0700-1700: 20 MW ----
135Nov-17/AP-45282-DA
04-Nov-17
APPCPL/103/2402
dt04-Nov-17
APPCPL
HPPC
-NPCL(UP)
05-Nov-17 05-Nov-17 0000-0600: 10 MW
0600-0700: 12 MW
1800-2000: 22 MW
2000-2100: 12 MW
2100-2400: 10 MW
----
136Nov-17/AP-45281-DA
04-Nov-17
NHPPL/NOV/05
dt04-Nov-17
NHPPL
NHPPL
-TPDDL
05-Nov-17 05-Nov-17 0000-0600: 2.7 MW
0600-0700: 2.75 MW
0700-1000: 2.7 MW
1000-1200: 2.75 MW
1200-1600: 2.7 MW
1600-1800: 2.75 MW
1800-2000: 2.7 MW
2000-2200: 2.75 MW
2200-2400: 2.7 MW
----
137Nov-17/AP-45280-DA
04-Nov-17
SHEPL/NOV/05
dt04-Nov-17
SHEPL_HP
SHEPL_HP
-TPDDL
05-Nov-17 05-Nov-17 0000-0900: 2.35 MW
0900-1200: 2.3 MW
1200-1600: 2.35 MW
1600-2300: 2.45 MW
2300-2400: 2.35 MW
----
138Nov-17/AP-45278-SD
03-Nov-17
NPCL/APPCPL/041117
dt03-Nov-17
NPCL(UP)
HPPC
-NPCL(UP)
04-Nov-17 04-Nov-17 0000-0600: 10 MW
0600-0700: 17 MW
0700-1000: 10 MW
1000-1100: 22 MW
1100-1300: 27 MW
1300-1500: 43 MW
1500-1700: 27 MW
1700-1800: 10 MW
1800-1900: 20 MW
1900-2000: 49 MW
2000-2100: 43 MW
2100-2200: 33 MW
2200-2300: 22 MW
2300-2400: 12 MW
----
139Nov-17/AP-45277-SD
03-Nov-17
PTC/OA/27802
dt03-Nov-17
PTC
SPDC-JK
-HPPC
04-Nov-17 04-Nov-17 0000-2400: 26.19 MW ----
140Nov-17/AP-45276-SD
03-Nov-17
SPT/OA/4615-DA
dt03-Nov-17
SCL
SCLTPS
-NPCL(UP)
04-Nov-17 04-Nov-17 0000-0100: 46 MW
0100-0300: 41 MW
0300-0500: 36 MW
0500-0600: 41 MW
0600-0700: 50 MW
0700-0800: 40 MW
0800-0900: 35 MW
0900-1700: 50 MW
1700-1800: 46 MW
1800-2400: 50 MW
----
141Nov-17/AP-45275-DA
03-Nov-17
APPCPL/103/2399
dt03-Nov-17
APPCPL
HPPC
-NPCL(UP)
04-Nov-17 04-Nov-17 0700-1700: 20 MW ----
142Nov-17/AP-45274-DA
03-Nov-17
BYPL/HP/Nov-17/DA-19
dt03-Nov-17
BYPL
HPSEB
-BYPL
04-Nov-17 04-Nov-17 1730-1800: 70 MW
1800-1900: 75 MW
1900-2000: 65 MW
2000-2030: 30 MW
----
143Nov-17/AP-45273-DA
03-Nov-17
MPPL/856/R/12213
dt03-Nov-17
MITTAL
HPPC
-HPSEB
04-Nov-17 04-Nov-17 0700-1200: 60 MW ----
144Nov-17/AP-45272-DA
03-Nov-17
MPPL/856/B/12212
dt03-Nov-17
MITTAL
HPSEB
-HPPC
04-Nov-17 04-Nov-17 1800-2000: 150 MW ----
145Nov-17/AP-45271-DA
03-Nov-17
02-BYPL/Nov-17(DA)
dt03-Nov-17
HPSEB
BYPL
-HPSEB
04-Nov-17 04-Nov-17 0630-0730: 50 MW
0730-0800: 20 MW
----
146Nov-17/AP-45279-DA
03-Nov-17
APPCPL/100/2400
dt03-Nov-17
APPCPL
MeSEB
-BYPL
04-Nov-17 04-Nov-17 0000-1000: 0 MW
1000-1300: 30 MW
1300-1700: 0 MW
1700-2000: 10 MW
2000-2400: 0 MW
NER-ER-NR
147Nov-17/AP-45270-DA
03-Nov-17
SHEPL/NOV/04
dt03-Nov-17
SHEPL_HP
SHEPL_HP
-TPDDL
04-Nov-17 04-Nov-17 0000-0100: 2.06 MW
0100-0300: 2.25 MW
0300-0600: 2.22 MW
0600-0900: 2.18 MW
0900-1300: 2.25 MW
1300-1500: 2.18 MW
1500-1800: 2.22 MW
1800-2300: 2.25 MW
2300-2400: 2.22 MW
----
148Nov-17/AP-45269-DA
03-Nov-17
NHPPL/NOV/04
dt03-Nov-17
NHPPL
NHPPL
-TPDDL
04-Nov-17 04-Nov-17 0000-0600: 2.7 MW
0600-0900: 2.65 MW
0900-1200: 2.7 MW
1200-1400: 2.65 MW
1400-1700: 2.7 MW
1700-2000: 2.65 MW
2000-2200: 2.8 MW
2200-2400: 2.65 MW
----
149Nov-17/AP-45268-SD
02-Nov-17
709406
dt02-Nov-17
ADANI
APL-Stage3
-RPPC
03-Nov-17 03-Nov-17 0000-2400: 263.5 MW WR-NR
150Nov-17/AP-45267-SD
02-Nov-17
709407
dt02-Nov-17
ADANI
APL-Stage1
-RPPC
03-Nov-17 03-Nov-17 0000-2400: 113.6 MW WR-NR
151Nov-17/AP-45266-SD
02-Nov-17
709408
dt02-Nov-17
ADANI
APL-Stage1
-RPPC
03-Nov-17 03-Nov-17 0000-2400: 48.95 MW WR-NR
152Nov-17/AP-45264-SD
02-Nov-17
PTC/OA/27801
dt02-Nov-17
PTC
SPDC-JK
-HPPC
03-Nov-17 03-Nov-17 0000-2400: 26.19 MW ----
153Nov-17/AP-45263-SD
02-Nov-17
NPCL/APPCPL/031117
dt02-Nov-17
NPCL(UP)
HPPC
-NPCL(UP)
03-Nov-17 03-Nov-17 0000-0400: 10 MW
0600-0700: 17 MW
1000-1100: 17 MW
1100-1200: 28 MW
1200-1300: 38 MW
1300-1400: 43 MW
1400-1500: 38 MW
1500-1600: 28 MW
1600-1700: 22 MW
1700-1800: 33 MW
1800-1900: 20 MW
1900-2000: 65 MW
2000-2100: 49 MW
2100-2200: 43 MW
2200-2300: 33 MW
2300-2400: 17 MW
----
154Nov-17/AP-45262-SD
02-Nov-17
SPT/OA/4614-DA
dt02-Nov-17
SCL
SCLTPS
-NPCL(UP)
03-Nov-17 03-Nov-17 0000-0100: 46 MW
0100-0300: 41 MW
0300-0400: 36 MW
0400-0600: 46 MW
0600-0700: 50 MW
0700-0800: 40 MW
0800-0900: 35 MW
0900-1800: 50 MW
1800-1900: 80 MW
1900-2400: 50 MW
----
155Nov-17/AP-45261-SD
02-Nov-17
APPCPL/103/2396
dt02-Nov-17
APPCPL
HPPC
-NPCL(UP)
03-Nov-17 03-Nov-17 0700-1700: 30 MW ----
156Nov-17/AP-45258-SD
02-Nov-17
IEX_171102_01252
dt02-Nov-17
IEX
JSWEL
-BYPL
02-Nov-17 02-Nov-17 0000-1700: 0 MW
1700-1800: 40 MW
1800-2400: 0 MW
SR-ER-NR
157Nov-17/AP-45265-DA
02-Nov-17
APPCPL/100/2395
dt02-Nov-17
APPCPL
MeSEB
-BYPL
03-Nov-17 03-Nov-17 0000-0700: 0 MW
0700-1700: 25 MW
1700-2400: 0 MW
NER-ER-NR
158Nov-17/AP-45260-DA
02-Nov-17
NHPPL/NOV/03
dt02-Nov-17
NHPPL
NHPPL
-TPDDL
03-Nov-17 03-Nov-17 0000-0500: 2.7 MW
0500-0900: 2.65 MW
0900-1200: 2.7 MW
1200-1400: 2.65 MW
1400-1700: 2.7 MW
1700-2000: 2.65 MW
2000-2200: 2.8 MW
2200-2400: 2.65 MW
----
159Nov-17/AP-45259-DA
02-Nov-17
SHEPL/NOV/03
dt02-Nov-17
SHEPL_HP
SHEPL_HP
-TPDDL
03-Nov-17 03-Nov-17 0000-0200: 2.22 MW
0200-0500: 2.14 MW
0500-0700: 2.1 MW
0700-0900: 2.14 MW
0900-1300: 2.22 MW
1300-1500: 2.14 MW
1500-1800: 2.18 MW
1800-2300: 2.25 MW
2300-2400: 2.22 MW
----
160Nov-17/AP-45257-SD
02-Nov-17
APPCPL/100/2394
dt02-Nov-17
APPCPL
MeSEB
-BYPL
02-Nov-17 02-Nov-17 0000-1400: 0 MW
1400-1700: 30 MW
1700-2400: 0 MW
NER-ER-NR
161Nov-17/AP-45256-SD
02-Nov-17
APPCPL/110/2393
dt02-Nov-17
APPCPL
APL-Stage1
-NPCL(UP)
02-Nov-17 02-Nov-17 0900-1000: 17 MW
1000-1100: 33 MW
1100-1200: 38 MW
1200-1300: 43 MW
1300-1500: 48 MW
1500-1600: 43 MW
1600-1700: 38 MW
1700-1800: 0 MW
1800-2000: 48.97 MW
WR-NR
162Nov-17/AP-45255-SD
01-Nov-17
709404
dt01-Nov-17
ADANI
THEP
-RPPC
02-Nov-17 02-Nov-17 0000-0900: 47 MW
0900-2100: 0 MW
2100-2400: 47 MW
ER-NR
163Nov-17/AP-45254-SD
01-Nov-17
PTC/OA/27800
dt01-Nov-17
PTC
SPDC-JK
-HPPC
02-Nov-17 02-Nov-17 0000-2400: 26.19 MW ----
164Nov-17/AP-45253-SD
01-Nov-17
NPCL/APPCPL/021117
dt01-Nov-17
NPCL(UP)
HPPC
-NPCL(UP)
02-Nov-17 02-Nov-17 0000-0100: 17 MW
0100-0200: 12 MW
0200-0300: 6 MW
0600-0700: 22 MW
0700-0800: 36 MW
0800-0900: 30 MW
0900-1700: 25 MW
1700-1800: 38 MW
2000-2100: 54 MW
2100-2200: 44 MW
2200-2300: 33 MW
2300-2400: 22 MW
----
165Nov-17/AP-45252-DA
01-Nov-17
SPT/OA/4613-DA
dt01-Nov-17
SCL
SCLTPS
-NPCL(UP)
02-Nov-17 02-Nov-17 0000-2400: 50 MW ----
166Nov-17/AP-45251-DA
01-Nov-17
BYPL/HP/Nov-17/DA-18
dt01-Nov-17
BYPL
HPSEB
-BYPL
02-Nov-17 02-Nov-17 1700-1730: 25 MW
1730-1900: 90 MW
1900-2000: 30 MW
----
167Nov-17/AP-45250-DA
01-Nov-17
01-BYPL/Nov-17(DA)
dt01-Nov-17
HPSEB
BYPL
-HPSEB
02-Nov-17 02-Nov-17 0700-0900: 75 MW
0900-0930: 55 MW
----
168Nov-17/AP-45249-DA
01-Nov-17
NHPPL/NOV/02
dt01-Nov-17
NHPPL
NHPPL
-TPDDL
02-Nov-17 02-Nov-17 0000-1000: 2.75 MW
1000-1400: 2.83 MW
1400-2000: 2.91 MW
2000-2400: 2.83 MW
----
169Nov-17/AP-45248-DA
01-Nov-17
SHEPL/NOV/02
dt01-Nov-17
SHEPL_HP
SHEPL_HP
-TPDDL
02-Nov-17 02-Nov-17 0000-0100: 1.95 MW
0100-0400: 1.9 MW
0400-0600: 1.85 MW
0600-0900: 1.9 MW
0900-1000: 1.85 MW
1000-1500: 1.9 MW
1500-1900: 2 MW
1900-2100: 1.9 MW
2100-2400: 1.95 MW
----
170Oct-17/AP-45240-SD
31-Oct-17
NHPPL/NOV/01
dt31-Oct-17
NHPPL
NHPPL
-TPDDL
01-Nov-17 01-Nov-17 0000-1000: 2.75 MW
1000-1400: 2.83 MW
1400-2000: 2.91 MW
2000-2400: 2.83 MW
----
171Oct-17/AP-45241-SD
31-Oct-17
709401
dt31-Oct-17
ADANI
APL-Stage1
-RPPC
01-Nov-17 01-Nov-17 0000-2400: 61.22 MW WR-NR
172Oct-17/AP-45232-SD
31-Oct-17
PTC/OA/27799
dt31-Oct-17
PTC
SPDC-JK
-HPPC
01-Nov-17 01-Nov-17 0000-2400: 26.19 MW ----
173Oct-17/AP-45238-SD
31-Oct-17
NPCL/APPCPL/011117
dt31-Oct-17
NPCL(UP)
SGPLNLR
-NPCL(UP)
01-Nov-17 01-Nov-17 0000-1400: 0 MW
1400-1500: 55 MW
1500-1600: 35 MW
1600-1700: 34 MW
1700-1800: 10 MW
1800-2000: 100 MW
2000-2100: 45 MW
2100-2200: 35 MW
2200-2300: 30 MW
2300-2400: 10 MW
SR-ER-NR
174Oct-17/AP-45237-SD
31-Oct-17
NPCL/APPCPL/0111172
dt31-Oct-17
NPCL(UP)
JITPL
-NPCL(UP)
01-Nov-17 01-Nov-17 0000-0100: 10 MW
0100-0500: 0 MW
0500-0600: 50 MW
0600-0700: 15 MW
0700-0800: 12 MW
0800-0900: 0 MW
0900-1000: 23 MW
1000-1100: 35 MW
1100-1200: 45 MW
1200-1300: 50 MW
1300-1400: 55 MW
1400-2400: 0 MW
ER-NR
175Oct-17/AP-45231-SD
31-Oct-17
APPCPL/103/2391
dt31-Oct-17
APPCPL
HPPC
-NPCL(UP)
01-Nov-17 01-Nov-17 0000-0500: 50 MW
0600-0700: 50 MW
0700-1700: 20 MW
1700-1800: 50 MW
2000-2400: 50 MW
----
176Oct-17/AP-45230-SD
31-Oct-17
APPCPL/103/2392
dt31-Oct-17
APPCPL
HPPC
-NPCL(UP)
01-Nov-17 01-Nov-17 0700-1700: 30 MW ----
177Oct-17/AP-45236-DA
31-Oct-17
APPCPL/94/2390
dt31-Oct-17
APPCPL
JHABUA
-NPCL(UP)
01-Nov-17 01-Nov-17 0000-0700: 0 MW
0700-1700: 10 MW
1700-2400: 0 MW
WR-NR
178Oct-17/AP-45229-DA
31-Oct-17
15-BYPL/Oct-17(DA)
dt31-Oct-17
HPSEB
BYPL
-HPSEB
01-Nov-17 01-Nov-17 0700-0900: 50 MW
0900-0930: 25 MW
----
179Oct-17/AP-45235-DA
31-Oct-17
MPPL/857/B/12204
dt31-Oct-17
MITTAL
CESC
-HPPC
01-Nov-17 01-Nov-17 0000-0500: 0 MW
0500-0615: 100 MW
0615-2400: 0 MW
ER-NR
180Oct-17/AP-45228-DA
31-Oct-17
BYPL/HP/Nov-17/DA-17
dt31-Oct-17
BYPL
HPSEB
-BYPL
01-Nov-17 01-Nov-17 1400-1700: 20 MW
1700-1730: 40 MW
1730-1930: 110 MW
1930-2030: 50 MW
----
181Oct-17/AP-45234-DA
31-Oct-17
APPCPL/107/2384/4
dt31-Oct-17
APPCPL
DOPGON
-TIHCL
01-Nov-17 01-Nov-17 0000-2400: .5 MW NER-ER-NR
182Oct-17/AP-45233-DA
31-Oct-17
APPCPL/107/2384/1
dt31-Oct-17
APPCPL
DOPGON
-BHMRC
01-Nov-17 01-Nov-17 0000-2400: .5 MW NER-ER-NR
183Oct-17/AP-45239-DA
31-Oct-17
APPCPL/107/2384/3
dt31-Oct-17
APPCPL
DOPGON
-BHSPL
01-Nov-17 01-Nov-17 0000-2400: .2 MW NER-ER-NR
184Oct-17/AP-45227-DA
31-Oct-17
SHEPL/NOV/01
dt31-Oct-17
SHEPL_HP
SHEPL_HP
-TPDDL
01-Nov-17 01-Nov-17 0000-0900: 1.9 MW
0900-1200: 1.85 MW
1200-1400: 1.9 MW
1400-1700: 2 MW
1700-2300: 2.05 MW
2300-2400: 2 MW
----
185Oct-17/AP-45226-FS
31-Oct-17
APPCPL/107/2357/2
dt30-Oct-17
APPCPL
DOPGON
-THNDPL
04-Nov-17 30-Nov-17 0000-2400: .3 MW NER-ER-NR
186Oct-17/AP-45225-FS
31-Oct-17
APPCPL/107/2357/4/R
dt30-Oct-17
APPCPL
DOPGON
-TIHCL
02-Nov-17 30-Nov-17 0000-2400: .5 MW NER-ER-NR
187Oct-17/AP-45224-FS
31-Oct-17
APPCPL/107/2357/3
dt30-Oct-17
APPCPL
DOPGON
-BHSPL
02-Nov-17 30-Nov-17 0000-2400: .2 MW NER-ER-NR
188Oct-17/AP-45223-FS
31-Oct-17
APPCPL/107/2357/1
dt30-Oct-17
APPCPL
DOPGON
-BHMRC
02-Nov-17 30-Nov-17 0000-2400: .5 MW NER-ER-NR
189Oct-17/AP-45210-FS
30-Oct-17
GBHPL/UPCL/01-101117
dt28-Oct-17
BUDHIL
BUDHIL
-UPCL
01-Nov-17 10-Nov-17 1200-1700: 60 MW ----
190Oct-17/AP-45209-FS
30-Oct-17
MPPL/855/12177
dt28-Oct-17
MITTAL
PSEB
-NPCL(UP)
01-Nov-17 30-Nov-17 0000-2400: 80 MW ----
191Oct-17/AP-45208-FS
30-Oct-17
APPCPL/103/2328
dt28-Oct-17
APPCPL
HPPC
-NPCL(UP)
01-Nov-17 19-Nov-17 0000-0700: 50 MW
0700-1700: 20 MW
1700-2400: 50 MW
----
20-Nov-17 30-Nov-17 0000-0700: 39 MW
0700-1700: 20 MW
1700-2400: 39 MW
----
192Oct-17/AP-45182-FS
27-Oct-17
APPCPL/77/105/2338
dt26-Oct-17
APPCPL
MeSEB
-JVVNL
01-Nov-17 30-Nov-17 0700-1700: 35 MW NER-ER-NR
193Oct-17/AP-45181-FS
27-Oct-17
MPPL/811/R/12123
dt27-Oct-17
MITTAL
HPPC
-HPSEB
01-Nov-17 15-Nov-17 0600-1800: 30 MW ----
16-Nov-17 30-Nov-17 0600-1800: 60 MW ----
194Oct-17/AP-45180-FS
27-Oct-17
MPPL/751/R/12083
dt27-Oct-17
MITTAL
BRPL
-HPSEB
01-Nov-17 15-Nov-17 0600-0900: 150 MW
0900-1800: 225 MW
1800-2200: 75 MW
----
16-Nov-17 30-Nov-17 0600-0900: 150 MW
0900-1800: 220 MW
1800-2200: 70 MW
----
195Oct-17/AP-45179-FS
27-Oct-17
PTC/OA/27773
dt27-Oct-17
PTC
PSEB
-JVVNL
01-Nov-17 30-Nov-17 0700-1700: 50 MW ----
196Oct-17/AP-45178-FS
27-Oct-17
APPCPL/106/2344
dt26-Oct-17
APPCPL
PSEB
-JVVNL
01-Nov-17 30-Nov-17 0700-1700: 50 MW ----
197Oct-17/AP-45177-FS
27-Oct-17
APPCPL/77/2327
dt26-Oct-17
APPCPL
HPPC
-JVVNL
01-Nov-17 30-Nov-17 0700-1700: 30 MW ----
198Oct-17/AP-45176-FS
27-Oct-17
NVVN/OA/12338
dt24-Oct-17
NVVN
BYPL
-J & K
01-Nov-17 30-Nov-17 0000-2400: 182.79 MW ----
199Oct-17/AP-45175-FS
27-Oct-17
MPPL/748/R/10864
dt24-Oct-17
MITTAL
BRPL
-HPSEB
01-Nov-17 30-Nov-17 0000-2400: 100 MW ----
200Oct-17/AP-45174-FS
27-Oct-17
YPL/2017-18/SKK/061
dt23-Oct-17
BSHP
BSHP
-DFPL
01-Nov-17 30-Nov-17 0000-2400: 1.2 MW ----
201Oct-17/AP-45173-FS
27-Oct-17
PTC/OA/27742
dt23-Oct-17
PTC
PSEB
-J & K
01-Nov-17 30-Nov-17 0000-2400: 350 MW ----
202Oct-17/AP-45137-AD
23-Oct-17
MPPL/808/R/12113
dt21-Oct-17
MITTAL
UPPCL
-HPSEB
01-Nov-17 15-Nov-17 0900-2200: 80 MW ----
16-Nov-17 30-Nov-17 0900-2200: 85 MW ----
203Oct-17/AP-45136-AD
23-Oct-17
4181/OAN/GMRETL/APPC
dt21-Oct-17
GMRETL
APPCC
-UPCL
01-Nov-17 30-Nov-17 1800-2300: 24.2 MW SR-ER-NR
204Oct-17/AP-45135-AD
23-Oct-17
PTC/OA/27735
dt16-Oct-17
PTC
BSHEP-JK
-NDMC
01-Nov-17 30-Nov-17 0000-2400: 1.02 MW ----
205Oct-17/AP-45134-AD
23-Oct-17

Rev.No: 1
NVVN/OA/12288
dt04-Oct-17
NVVN
JITPL
-J & K
01-Nov-17 05-Nov-17 1800-2300: 30 MW ER-NR
206Sep-17/AP-44785-AD
26-Sep-17
APPCPL/53/891
dt12-Sep-17
APPCPL
BRPL
-HPSEB
01-Nov-17 15-Nov-17 0000-0600: 160 MW
2200-2400: 160 MW
----
16-Nov-17 30-Nov-17 0000-0600: 160 MW
2200-2400: 160 MW
----
207Sep-17/AP-43879-AD
01-Sep-17
3656/OAN/GMRETL/APPC
dt31-Aug-17
GMRETL
APPCC
-UPCL
01-Nov-17 30-Nov-17 0000-1800: 24.2 MW
2300-2400: 24.2 MW
SR-ER-NR
208Sep-17/AP-43878-AD
01-Sep-17

Rev.No: 1
NVVN/OA/12163
dt31-Aug-17
NVVN
JITPL
-J & K
01-Nov-17 11-Nov-17 0000-1800: 30 MW
1800-2300: 0 MW
2300-2400: 30 MW
ER-NR