| S.No |
Element Name |
Type |
Voltage Level |
Owner |
Outage |
Revival |
Expected Date of Revival |
Reason / Remarks |
| Date |
Time |
Date |
Time |
| 1 |
Fatehpur 1500 MVA ICT 1 |
ICT |
765/400 kV |
PGCIL |
10-09-2016 |
15:58 |
10-09-2016 |
18:36 |
- |
For CSD Commissioning . |
| 2 |
765 kV Bhiwani-2 / ICT-2 Tie Bay(702-52T) at Phagi |
BAY/CB |
765 kV |
RRVPNL |
23-08-2016 |
11:07 |
* |
* |
11-09-2016 |
For erection and commissioning of Bhiwani-II main bay equipments at Phagi |
| 3 |
765 kV / 400kV ICT-1 Main Bay (703) at Fatehpur PG |
BAY/CB |
765 kV |
PGCIL |
10-09-2016 |
10:54 |
10-09-2016 |
12:45 |
- |
For CSD Commissioning works. |
| 4 |
765 kV Gaya-1/ ICT-1 Tie Bay (702) at Fatehpur PG |
BAY/CB |
765 kV |
PGCIL |
10-09-2016 |
13:06 |
10-09-2016 |
18:36 |
- |
For CSD Commissioning works. |
| 5 |
Ballabgarh-Kanpur 1 |
Line |
400 kV |
PGCIL |
10-09-2016 |
09:15 |
10-09-2016 |
19:46 |
- |
For replacement of Tie Bay isolator( Ballabhagarh -1 Line side-41689A) at Kanpur PG under Add Cap |
| 6 |
400kV G.Noida(UP)-Nawada(HVPNL) |
Line |
400 kV |
PGCIL |
10-09-2016 |
09:56 |
10-09-2016 |
15:44 |
- |
To replace the 400kV Isolator blades at Nawada and maintenance of isolator of Bus-1 at Nawada by HVPNL. |
| 7 |
Daultabad(HVPNL)-Gurgaon(PG) -1 |
Line |
400 kV |
HVPNL |
10-09-2016 |
10:40 |
10-09-2016 |
19:02 |
- |
For GIS Bay-408 AMP Works at Gurgaon end by Powergrid NR-1. |
| 8 |
Kankroli-Zerda |
Line |
400 kV |
PGCIL |
10-09-2016 |
15:05 |
10-09-2016 |
15:38 |
- |
To take line reactor Out of service at Kankroli end. |
| 9 |
Kankroli-Zerda |
Line |
400 kV |
PGCIL |
10-09-2016 |
19:11 |
10-09-2016 |
19:28 |
- |
To take line reactor In serviceat Kankroli end. |
| 10 |
Ballabgarh 315 MVA ICT 2 |
ICT |
400/220 kV |
PGCIL |
08-08-2016 |
10:26 |
* |
* |
11-09-2016 |
For retrofittment ( replacement for capacity addition) of this 315 MVA ICT 2 with new 500MVA ICT 2 at Ballabhagarh PG. |
| 11 |
New Wanpoh 125 MVAR B/Reactor 1 |
Bus Reactor |
400 kV |
PGCIL |
27-04-2015 |
18:29 |
* |
* |
NA |
Take out due to low voltage. |
| 12 |
Kisanpur 80 MVAR B/R |
Bus Reactor |
400 kV |
PGCIL |
02-02-2016 |
08:05 |
* |
* |
NA |
For voltage regulation. |
| 13 |
Nawada 400 kV Bus 1 |
BUS |
400 kV |
HVPNL |
10-09-2016 |
10:09 |
10-09-2016 |
15:44 |
- |
To replace the 400kV Isolator blades of Gr.Noida-Nawada line bay at Nawada and maintenance of isolator of Bus-1 at Nawada by HVPNL. |
| 14 |
Kanpur(PG)-Unchahar(NTPC) 1 |
Line |
220 kV |
PGCIL |
01-09-2016 |
12:01 |
10-09-2016 |
13:29 |
- |
For complete replacement of protection panes by numerical relays module at Unchahar end by NTPC. |
| 15 |
Mainpuri(PG)-Mainpuri(UP) 1 |
Line |
220 kV |
UPPTCL |
09-09-2016 |
16:38 |
* |
* |
NA |
Replacement of CVT. |
| 16 |
FSC of Pampore-1 at Kishnpr |
FSC |
220 kV |
PGCIL |
30-10-2012 |
12:00 |
* |
* |
NA |
LILO work of line . |
| 17 |
FSC of Pampore-2 at Kishnpr |
FSC |
220 kV |
PGCIL |
30-10-2012 |
12:00 |
* |
* |
NA |
LILO work of line . |