| S.No |
Element Name |
Type |
Voltage Level |
Owner |
Outage |
Revival |
Expected Date of Revival |
Reason / Remarks |
| Date |
Time |
Date |
Time |
| 1 |
Balia-Bhiwadi Pole 1 |
Line |
500 kV HVDC |
PGCIL |
02-12-2011 |
21:33 |
* |
* |
NA |
Construction of new element . |
| 2 |
Dadri(NTPC)-Panipat(BBMB) 1 |
Line |
400 kV |
PGCIL |
02-12-2011 |
08:01 |
03-12-2011 |
20:46 |
- |
Diversion work at tower location No. 35. |
| 3 |
Baspa(HP)-Karchamwangtoo(JP) 1 |
Line |
400 kV |
JPHYDRO |
02-12-2011 |
23:40 |
03-12-2011 |
06:28 |
- |
Maintenance work. |
| 4 |
Baspa(HP)-Karchamwangtoo(JP) 2 |
Line |
400 kV |
JPHYDRO |
02-12-2011 |
23:41 |
03-12-2011 |
06:28 |
- |
Maintenance work. |
| 5 |
Jhakri(SJVNL)-Karchamwangtoo(JP) 2 |
Line |
400 kV |
JPHYDRO |
02-12-2011 |
23:42 |
04-12-2011 |
06:16 |
- |
Maintenance work. |
| 6 |
Jhakri(SJVNL)-Karchamwangtoo(JP) 1 |
Line |
400 kV |
JPHYDRO |
02-12-2011 |
23:42 |
03-12-2011 |
06:39 |
- |
Maintenance work. |
| 7 |
Dadri(NTPC)-Muradnagar(UP) |
Line |
400 kV |
PGCIL |
03-12-2011 |
08:00 |
03-12-2011 |
21:19 |
- |
Railway diversion work. |
| 8 |
Agra(PG)-Auraiya(NTPC) 2 |
Line |
400 kV |
PGCIL |
03-12-2011 |
09:44 |
03-12-2011 |
18:23 |
- |
Construction of new element . |
| 9 |
Fatehabad(PG)-Khedar(HVPNL) 1 |
Line |
400 kV |
HVPNL |
03-12-2011 |
10:37 |
03-12-2011 |
18:23 |
- |
Planned annual maintenance. |
| 10 |
Bareilly(PG)-Lucknow(UP) |
Line |
400 kV |
PGCIL |
03-12-2011 |
10:44 |
03-12-2011 |
19:13 |
- |
Planned annual maintenance. |
| 11 |
Kishenpur-Wagoora 1 |
Line |
400 kV |
PGCIL |
03-12-2011 |
11:03 |
03-12-2011 |
18:36 |
- |
To replace conductor |
| 12 |
Ballabgarh-Gurgaon |
Line |
400 kV |
PGCIL |
03-12-2011 |
12:28 |
03-12-2011 |
16:44 |
- |
Retrofitment of new relay at BLB end. |
| 13 |
Baglihar(JK)-Kishenpur(PG) 1 |
Line |
400 kV |
PDD JK |
03-12-2011 |
19:01 |
* |
* |
NA |
Testing at Baglihar end |
| 14 |
Baspa(HP)-Karchamwangtoo(JP) 2 |
Line |
400 kV |
JPHYDRO |
03-12-2011 |
23:04 |
04-12-2011 |
06:26 |
- |
Cable laying at Kacrcham end. |
| 15 |
Jhakri(SJVNL)-Karchamwangtoo(JP) 1 |
Line |
400 kV |
JPHYDRO |
03-12-2011 |
23:04 |
04-12-2011 |
06:16 |
- |
Cable laying at Karcham end. |
| 16 |
Baspa(HP)-Karchamwangtoo(JP) 1 |
Line |
400 kV |
JPHYDRO |
03-12-2011 |
23:15 |
04-12-2011 |
06:26 |
- |
Cable laying at Kacham end. |
| 17 |
Debari(RVPNL)-RAPS B(NPC) |
Line |
220 kV |
PGCIL |
01-12-2011 |
12:45 |
* |
* |
NA |
Line Diversion work |
| 18 |
Sultanpur(UP)-Tanda(NTPC) 2 |
Line |
220 kV |
UPPTCL |
03-12-2011 |
09:28 |
03-12-2011 |
18:52 |
- |
Planned annual maintenance. |
| 19 |
Bassi(PG)-Kukas(RVPNL) |
Line |
220 kV |
RRVPNL |
03-12-2011 |
10:25 |
03-12-2011 |
15:24 |
- |
S/D by RRVPNL for Maintenance work. |