| Sl.No. |
Station |
Voltage / MVA |
Outage Date |
Outage Time |
Revival Date |
Revival Time |
Reasons for Outage |
| A. Central Sector |
| 1 |
Dehar - Panipat |
500 |
28-Dec-2010 |
00:10 |
28-Dec-2010 |
8:48 |
Manually opened due to High voltage |
| 2 |
Chamera - Jalandhar - II |
400 |
27-Dec-2010 |
21:32 |
28-Dec-2010 |
8:01 |
Manually opened due to High voltage |
| 3 |
Jalandhar - Moga -II |
400 |
27-Dec-2010 |
21:28 |
28-Dec-2010 |
8:03 |
Manually opened due to High voltage |
| 4 |
Abdullapur-Bawana -I |
400 |
27-Dec-2010 |
23:48 |
28-Dec-2010 |
7:53 |
Manually opened due to High voltage |
| 5 |
Moga - Bhiwadi-I |
400 |
27-Dec-2010 |
23:38 |
28-Dec-2010 |
8:17 |
Manually opened due to High voltage |
| 6 |
Nalagarh - NJPC - I |
400 |
27-Dec-2010 |
23:48 |
28-Dec-2010 |
8:30 |
Manually opened due to High voltage |
| 7 |
Moga - Fathehabad |
400 |
28-Dec-2010 |
9:47 |
28-Dec-2010 |
18:17 |
S/D : Polymer Insulator installation work |
| 8 |
Kota -Merta - I |
400 |
27-Dec-2010 |
19:01 |
28-Dec-2010 |
13:48 |
Manually opened due to High voltage |
| 9 |
Nalagarh - Kaithal |
400 |
27-Dec-2010 |
22:29 |
28-Dec-2010 |
6:30 |
Manually opened due to High voltage |
| 10 |
Nalagarh - Kaithal |
400 |
28-Dec-2010 |
9:45 |
28-Dec-2010 |
19:30 |
S/D : Polymer Insulator installation work |
| 11 |
Baamanauli - Mundka-I |
400 |
28-Dec-2010 |
10:15 |
28-Dec-2010 |
14:09 |
S/D : Polymer Insulator installation work |
| 12 |
Dehar-Bhiwani |
400 |
27-Dec-2010 |
21:01 |
28-Dec-2010 |
7:48 |
Manually opened due to High voltage |
| 13 |
Nalagarh - NJPC - II |
400 |
27-Dec-2010 |
20:20 |
28-Dec-2010 |
5:29 |
Manually opened due to High voltage |
| 14 |
Balia - Patna-I |
400 |
28-Dec-2010 |
2:02 |
28-Dec-2010 |
9:28 |
Manually opened due to High voltage |
| 15 |
Kishenpur - Wagoora - II |
400 |
28-Dec-2010 |
10:50 |
28-Dec-2010 |
14:32 |
S/D for replacement of Damge insulater |
| 16 |
Agra - Bassi - III |
400 |
27-Dec-2010 |
21:34 |
28-Dec-2010 |
7:18 |
Manually opened due to High voltage |
| 17 |
Agra - Bhiwadi - II |
400 |
27-Dec-2010 |
21:33 |
28-Dec-2010 |
7:16 |
Manually opened due to High voltage |
| 18 |
Bassi - Bhiwadi - II |
400 |
27-Dec-2010 |
21:34 |
28-Dec-2010 |
7:19 |
Manually opened due to High voltage |
| 19 |
|
|
|
|
|
|
|
| 20 |
|
|
|
|
|
|
|
| 21 |
|
|
|
|
|
|
|
| 22 |
|
|
|
|
|
|
|
| 23 |
|
|
|
|
|
|
|
| 24 |
|
|
|
|
|
|
|
| 25 |
|
|
|
|
|
|
|
| 26 |
|
|
|
|
|
|
|
| B. State Sector |
| 1 |
Obra - Panki |
400 |
28-Dec-2010 |
9:47 |
28-Dec-2010 |
18:08 |
S/D : Line maintenance. |
| 2 |
Anpara - Sarnath - II |
400 |
28-Dec-2010 |
11:55 |
28-Dec-2010 |
20:10 |
S/D : Line maintenance. |
| 3 |
Unnao - Bareilly - I |
400 |
28-Dec-2010 |
10:28 |
28-Dec-2010 |
18:58 |
S/D : Line maintenance. |
| 4 |
Panki - Muradnagar |
400 |
28-Dec-2010 |
13:05 |
28-Dec-2010 |
13:51 |
Tripped due to Trasient fault |
| 5 |
Unao - Agra |
400 |
28-Dec-2010 |
9:47 |
28-Dec-2010 |
22:10 |
S/D : Line maintenance. |
| 6 |
|
|
|
|
|
|
|
| 7 |
|
|
|
|
|
|
|
| 8 |
|
|
|
|
|
|
|
| 9 |
|
|
|
|
|
|
|
| 10 |
|
|
|
|
|
|
|
| 11 |
|
|
|
|
|
|
|
| 12 |
|
|
|
|
|
|
|
| 13 |
|
|
|
|
|
|
|
| 14 |
|
|
|
|
|
|
|
| 15 |
|
|
|
|
|
|
|
| 16 |
|
|
|
|
|
|
|
| 17 |
|
|
|
|
|
|
|
| 18 |
|
|
|
|
|
|
|
| 19 |
|
|
|
|
|
|
|
| 20 |
|
|
|
|
|
|
|
| Sl.No. |
Name of Line |
Voltage Level |
Outage Date |
Outage Time |
Expected Revival Date |
Reason of Outage |
| A. Central Sector |
| 1 |
Abdullapur - NJPC - I |
400 |
20/11/2009 |
4:56 |
-- |
C.B Problem at NJPC End |
| 2 |
Koldam - Nalagarh - I & II |
400 |
01/04/2010 |
2:11 |
-- |
Opened on H/V.Presently lines are under S/D & not yet commercialized. |
| 3 |
Roorkee - Rishikesh |
400 |
09/08/2010 |
4:03 |
-- |
Tripped on R & Y - N Fault.(Now Tower collapsed to be attended by UPCL). |
| 4 |
Kankroli - Jodhpur |
400 |
27/12/2010 |
20:34 |
-- |
Manually opened due to High voltage |
| 5 |
Balia - Biharsharif -II |
400 |
17/12/2010 |
20:36 |
-- |
Manually opened due to High voltage |
| 6 |
Agra - Ballabhgarh |
400 |
25/12/2010 |
08:13 |
-- |
S/D: Line diversion work on KMP Expressway /Polymer Insulator installation. |
| 7 |
Lucknow-Gorakhpur-II |
400 |
25/12/2010 |
22:09 |
-- |
Manually opened due to High voltage |
| 8 |
Lucknow-Gorakhpur-III |
400 |
27/12/2010 |
21:43 |
-- |
Manually opened due to High voltage |
| 9 |
Gorakhpur - Muzaffarpur - I |
400 |
18/12/2010 |
17:25 |
-- |
Manually opened due to High voltage |
| 10 |
Bareilly - Mandola - II |
400 |
27/12/2010 |
10:20 |
-- |
S/D : Restoration of new tower from ERS. |
| 11 |
Kota -Merta - I |
400 |
28.12.2010 |
18.24 |
- |
Manually opened due to High voltage |
| 12 |
Balia - Patna-I |
400 |
28/12/2010 |
18.26 |
- |
Manually opened due to High voltage |
| 13 |
Dehar-Bhiwani |
400 |
28-Dec-2010 |
20.51 |
- |
Manually opened due to High voltage |
| 14 |
Nalagarh - Kaithal |
400 |
28-Dec-2010 |
21.48 |
- |
Manually opened due to High voltage |
| 15 |
Jallandhar - Chamera -I |
400 |
28-Dec-2010 |
22.44 |
- |
Manually opened due to High voltage |
| 16 |
Jallandhar -Moga - I |
400 |
28-Dec-2010 |
22.42 |
- |
Manually opened due to High voltage |
| 17 |
Nallagarh - NJPC- I |
400 |
28-Dec-2010 |
20.49 |
- |
Manually opened due to High voltage |
| 18 |
Nallagarh - NJPC- II |
400 |
28-Dec-2010 |
23:48 |
- |
Manually opened due to High voltage |
| 19 |
Bassi - Bhiwadi - I |
400 |
28-Dec-2010 |
21.46 |
- |
Manually opened due to High voltage |
| 20 |
Lucknow-Gorakhpur-IV |
400 |
28-Dec-2010 |
22:53 |
- |
Manually opened due to High voltage |
| 21 |
Abdullapur - Bawana - II |
400 |
28-Dec-2010 |
22.01 |
|
Manually opened due to High voltage |
| 22 |
RAAP -C Kankrauli - I |
400 |
28-Dec-2010 |
22.34 |
- |
Manually opened due to High voltage |
| 23 |
Dehar-Panipat |
400 |
28-Dec-2010 |
22.28 |
-- |
Manually opened due to High voltage |
| 24 |
Moga - Bhiwadi-I |
400 |
28-Dec-2010 |
22.38 |
- |
Manually opened due to High voltage |
| 25 |
Agra - Bassi - III |
400 |
28-Dec-2010 |
22.53 |
- |
Manually opened due to High voltage |
| 26 |
Kanpur-Ballabhgarh-II |
400 |
28-Dec-2010 |
23.32 |
- |
Manually opened due to High voltage |
| 27 |
Balia - Bhiwadi -I |
500 |
29-Dec-2010 |
00.02 |
- |
Manually opened due to High voltage |
| 28 |
Allahabad - Sasaram |
400 |
28-Dec-2010 |
17:55 |
- |
Manually opened due to High voltage |
| B. State Sector |
| 1 |
50MVARbus Reacter at Lko ( UP) |
400 |
10-Jul-2008 |
00.46 |
-- |
Bushing damage. reactor decapitalised by Powergrid. |
| 2 |
50 MVAR bus Reactor at Bareilly (UP) |
400 |
05-Aug-2007 |
0:00 |
-- |
Reactor windings damaged. To be replaced by new. |
| 3 |
Bus Reactor at Sarnath. |
400 |
16-Feb-2009 |
6:14 |
-- |
Under Breakdown |
| 4 |
Baspa - NJPC - II |
400 |
28-Dec-2010 |
21:46 |
- |
Manually opened due to High voltage |
| 5 |
|
|
|
|
|
|
| 6 |
|
|
|
|
|
|
| 7 |
|
|
|
|
|
|
| 8 |
|
|
|
|
|
|
| 9 |
|
|
|
|
|
|
| 10 |
|
|
|
|
|
|
| 11 |
|
|
|
|
|
|
| 12 |
|
|
|
|
|
|
| 13 |
|
|
|
|
|
|
| 14 |
|
|
|
|
|
|
| 15 |
|
|
|
|
|
|
| 16 |
|
|
|
|
|
|
| 17 |
|
|
|
|
|
|
| 18 |
|
|
|
|
|
|
| 19 |
|
|
|
|
|
|
| 20 |
|
|
|
|
|
|