Transmission Elements Outage Report for 20-11-2016

A. Details of Transmission Elements under Planned Outage:-
S.No Element Name Type Voltage Level Owner Outage Revival Expected Date of Revival Reason / Remarks
Date Time Date Time
1 Jatikala-Kanpur New Line 765 kV PGCIL 20-11-2016 07:47 20-11-2016 19:09 - For jumper tightening / CC VD fixing
2 765 kV Bus Reactor -1 Main Bay (703) at Moga PG BAY/CB 765 kV PGCIL 19-11-2016 09:45 * * 20-11-2016 For AMP of bays equipments.
3 Agra-Bhiwadi 2 Line 400 kV PGCIL 14-11-2016 11:14 * * 22-11-2016 Diverson of Line --- for tower erection and diversion works due to infringement in DFCC corridor ( work is being done by Powergrid)
4 Agra-Bhiwadi 1 Line 400 kV PGCIL 14-11-2016 11:14 * * 22-11-2016 Diverson of Line --- for tower erection and diversion works due to infringement in DFCC corridor ( work is being done by Powergrid)
5 Lucknow-Unnao Line 400 kV UPPTCL 20-11-2016 08:09 20-11-2016 19:46 - For complete over hauling of 29 A and 29 C isolator of Lucknow UP line at Unnao end along with the 29 A isolator of Bus coupler at Unbao.
6 Bhinmal-Zerda Line 400 kV PGCIL 20-11-2016 09:56 20-11-2016 16:06 - Shutdown by WRLDC.
7 Dhuri (400kV)-Rajpura (400kV)-2 Line 400 kV PSEB 20-11-2016 10:07 * * 21-11-2016 Tightening of jumpers ,dampers, suspension clamps and cleaning of disc insulator in the line between loc no.81 to 96 by PSTCL.
8 Muzaffarnagar-Vishnuprayag 1 Line 400 kV UPPTCL 20-11-2016 11:31 20-11-2016 18:35 - Polymer insulator replacement--- for replacement of porcelain disc insulators with polymer insulators strings in the line.
9 Dehar 250 MVA ICT ICT 400/220 kV BBMB 15-10-2016 08:02 * * 11-12-2016 Construction of new element For replacement of 400/220 ,250 MVA ICT (3*83.3 MVA + one spare unit 83.3 MVA) and its associate bay equipments with 315 MVA ICT (3*105 MVA + I spare unit 105 MVA) Transformers of 400/220 KV CGL make under Northern Region Strengthening Scheme at BBMB Dehar.The replacement work will be carried out by PGCIL.
10 Dhuri(400) 500 MVA ICT 2 ICT 400/220 kV PSEB 17-11-2016 10:26 * * 23-11-2016 Emergency SD for Complete internal inspection due to Detection of high C2H2 from the test result of PD test conducted at site
11 Nakodar 315 MVA ICT 2 ICT 400/220 kV PSEB 19-11-2016 08:43 20-11-2016 16:45 - Completion, testing and commissioning of HVWSS system
12 TCSC of MUZPR-I at GRKP TCSC 400 kV PGCIL 17-09-2016 11:23 * * NA Block problem of Y &B phase.
13 Jalandhar(PG) 125 MVAR (400kV) Bus Reactor 1 Bus Reactor 400 kV PGCIL 07-10-2016 11:03 * * 30-11-2016 For shifting of Bus reactor in ICT-3 diafor vacating its bays for LILO of 400kV Amritsar-Parbati line at Jalandhar by Powergrid.
14 New Wanpoh 125 MVAR B/Reactor 1 Bus Reactor 400 kV PGCIL 10-10-2016 10:09 * * NA Take out due to low voltage.
15 FSC ( 50% ) of Koteshwar Pool -1 at Meerut (PG) FSC 400 kV PGCIL 04-11-2016 09:10 * * 30-11-2016 To facilitating Bay extension works at Meerut and erection works of 02 nos of dead end tower.
16 Sultanpur 400 kV Bus 1 BUS 400 kV UPPTCL 07-11-2016 13:15 * * 30-11-2016 For erection and commissioning of new Bus bar protection panel in place of old Bus Bar protection panel.
17 Bikaner 400 kV Bus 1 BUS 400 kV RRVPNL 15-11-2016 11:50 20-11-2016 16:19 - Jumpering and maintenance works.
18 Koteshwar Pool 400 kV Bus 1 BUS 400 kV PGCIL 19-11-2016 09:57 * * 21-11-2016 Replacement of isolator contacts of Tehri-2 line at Koteshwar(PG)-GIS With Bus-1.
19 Unnao 400 kV Bus 1 BUS 400 kV UPPTCL 20-11-2016 08:09 20-11-2016 19:46 - For complete over hauling of 29 A and 29 C isolator of Lucknow UP line at Unnao end along with the 29 A isolator of Bus coupler at Unbao.
20 Patiala(PG)-Rajpura(PSEB) Line 220 kV PSEB 11-11-2016 13:05 * * 26-11-2016 To augment present single 220kv Busbar with double 220kv Busbar at Rajpura PSTCL.
21 AD Hydro(ADHY)-Nallagarh(PG) 1 Line 220 kV ADHYDRO 20-11-2016 10:34 20-11-2016 17:42 - 1.For Pre-winter maintenance works ( tightening of jumpers, tower parts,VD & cleaning of insulators etc , and lopping /chopping of trees and rectification of loose sags if any.
22 FSC of Pampore-2 at Kishnpr FSC 220 kV PGCIL 30-10-2012 12:00 * * NA Line length has reduced after LILO work completion
23 FSC of Pampore-1 at Kishnpr FSC 220 kV PGCIL 30-10-2012 12:00 * * NA Line length has reduced after LILO work completion
*-Line still under outage     NA - Not Available

B. Details of Transmission Elements under Forced Outage:-
S.No Element Name Type Voltage Level Owner Outage Revival Expected Date of Revival Reason / Remarks
Date Time Date Time
1 G.Noida 765 (3*80) 240 MVAR (765kV) Bus Reactor 1 Bus Reactor 765 kV UPPTCL 06-08-2016 10:32 * * NA To attend hot spot To attend Buchholz alarm in R phase
2 Bamnauli(DTL)-Jatikala(PG) 1 Line 400 kV DTL 22-05-2016 20:29 * * NA Tower damage (First dead end tower from Bamnauli S/S) / Ckt-II charge through ERS tower
3 Bikaner-Merta Line 400 kV RRVPNL 11-11-2016 16:09 * * NA Tripped on High voltage.
4 Fatehabad-Hisar Line 400 kV PGCIL 19-11-2016 19:56 * * NA Tripped on High voltage.
5 Khedar-Nuhiyawali 2 Line 400 kV HVPNL 19-11-2016 20:39 * * NA Tripped on High voltage.
6 Nakodar - Talwandi Sabo-1 Line 400 kV PSEB 19-11-2016 23:42 * * NA Tripped on High voltage.
7 Dadri(NTPC)-Maharanibagh(PG) Line 400 kV PGCIL 20-11-2016 03:03 20-11-2016 04:52 - Tripped on High voltage.
8 Ballabgarh-Maharanibagh Line 400 kV PGCIL 20-11-2016 03:05 20-11-2016 04:57 - Tripped on High voltage.
9 Anpara-Sarnath 1 Line 400 kV UPPTCL 20-11-2016 08:25 20-11-2016 12:06 - Phase to phase fault/ R-Y.
10 Ballabgarh(PG)-Bamnauli(DTL) 2 Line 400 kV DTL 20-11-2016 13:10 20-11-2016 14:04 - Phase to earth fault/ R Phase.
11 Mainpuri(PG)-Orai 400(UP)-1 Line 400 kV UPPTCL 20-11-2016 18:23 20-11-2016 19:51 - Phase to earth fault/ Y Phase
12 Orai 400-Paricha TPS-1 Line 400 kV UPPTCL 20-11-2016 18:36 20-11-2016 19:59 - Phase to earth fault.
13 Kalisindh 315 MVA ICT ICT 400/220 kV RRVPNL 04-06-2016 15:50 * * NA Buchholz relay operated.
14 Alwar II 315 MVA ICT 1 ICT 400/220 kV RRVPNL 09-11-2016 12:15 * * NA Due to oil leakage.
15 Nuhiyawali 315 MVA ICT 1 ICT 400/220 kV HVPNL 16-11-2016 21:19 * * NA Tripped on High voltage.
16 Muzaffarnagar 240 MVA ICT 2 ICT 400/220 kV UPPTCL 20-11-2016 19:18 * * NA Phase to earth faultDue to sparking in B phase isolator.
17 Bareilly 50 MVAR B/R Bus Reactor 400 kV UPPTCL 05-08-2007 00:00 * * NA Failure of Reactor.
18 Sarnath 50 MVAR B/R Bus Reactor 400 kV UPPTCL 16-02-2009 06:14 * * NA Failure of Reactor.
19 FSC of Bareilly-I at Unnao FSC 400 kV PGCIL 19-04-2015 13:10 * * NA Fire in FSC.
20 Wagoora 50 MVAR B/R Bus Reactor 400 kV PGCIL 22-04-2015 18:56 * * NA Take out due to low voltage.
21 FSC ( 50% ) of Koteshwar Pool -2 at Meerut (PG) FSC 400 kV PGCIL 16-07-2015 13:01 * * NA Fire in FSC-2 at Meerut.
22 FACT at BLB in Knp-BLB Line FACTS 400 kV PGCIL 02-07-2016 10:20 * * NA Y-Phase current imbalance
23 Sewa II - Hiranagar 1 Line 132 kV PDD JK 20-11-2016 12:19 20-11-2016 17:42 - Due to sparking at R-phase
*-Line still under outage     NA - Not Available

C. Details of Transmission Elements Opened manually due to High Voltage:-
S.No Element Name Type Voltage Level Owner Outage Revival Remarks
Date Time Date Time
1 Agra-Fatehpur 2 Line 765 kV PGCIL 19-11-2016 19:31 20-11-2016 09:02  
2 Meerut - Moga Line 765 kV PGCIL 19-11-2016 21:03 21-11-2016 09:35  
3 Bhiwani -Meerut Line 765 kV PGCIL 19-11-2016 21:13 21-11-2016 09:14  
4 Agra-Fatehpur Line 765 kV PGCIL 20-11-2016 20:11 21-11-2016 09:19  
5 Dhuri(400kv) -Rajpura (TH) -1 Line 400 kV PSEB 08-11-2016 03:04 ** **  
6 Dhuri(400kv) -Talwandi Sabo 1 Line 400 kV PSEB 08-11-2016 21:32 ** **  
7 Mukatsar -Talwandi Sabo - 2 Line 400 kV PSEB 09-11-2016 21:34 ** **  
8 Makhu -Mukatsar -2 Line 400 kV PSEB 09-11-2016 21:36 ** **  
9 Ajmer II-Didwana Line 400 kV RRVPNL 11-11-2016 12:35 20-11-2016 06:46  
10 Kaithal(PG)-Patran(PTCL) 1 Line 400 kV PGCIL 14-11-2016 01:13 ** **  
11 Fatehabad(PG)-Khedar(HVPNL) 1 Line 400 kV HVPNL 15-11-2016 20:20 ** **  
12 Amritsar(PG)-Makhu(PSEB) -1 Line 400 kV PSEB 16-11-2016 21:50 21-11-2016 13:06  
13 Bhiwadi - Hisar 2 Line 400 kV PGCIL 17-11-2016 16:24 ** **  
14 Neemrana-Sikar 2 Line 400 kV PGCIL 17-11-2016 20:00 20-11-2016 07:10  
15 Baghpat-Kaithal 2 Line 400 kV PGCIL 18-11-2016 01:12 ** **  
16 Makhu -Nakodar -1 Line 400 kV PSEB 18-11-2016 03:24 ** **  
17 Ratangarh (RVPNL) - Sikar (PG) - 1 Line 400 kV PGCIL 18-11-2016 17:40 20-11-2016 09:51  
18 Chamera pool-Jalandhar 1 Line 400 kV PGCIL 18-11-2016 19:46 20-11-2016 07:19  
19 Neemrana-Sikar 1 Line 400 kV PGCIL 18-11-2016 19:46 ** **  
20 Kurukshetra(PG)-Sonipat 1 Line 400 kV PGCIL 18-11-2016 19:47 ** **  
21 Fatehabad-Moga Line 400 kV PGCIL 18-11-2016 19:51 20-11-2016 08:42  
22 Chittorgarh II(RVPNL)-Kankroli(PG) Line 400 kV PGCIL 18-11-2016 22:05 ** **  
23 Chittorgarh II(RVPNL)-RAPS C(NPC) Line 400 kV PGCIL 18-11-2016 22:05 ** **  
24 Jalandhar-( by passing Samba )-Kisanpur Line 400 kV PGCIL 18-11-2016 22:09 ** **  
25 Jalandhar-Kurukshetra(PG) 1 Line 400 kV PGCIL 18-11-2016 22:10 ** **  
26 Jalandhar-Ludhiana Line 400 kV PGCIL 18-11-2016 22:13 20-11-2016 08:39  
27 Ratangarh (RVPNL) - Sikar (PG) - 2 Line 400 kV PGCIL 19-11-2016 16:09 21-11-2016 06:31  
28 Bikaner-Didwana 1 Line 400 kV RRVPNL 19-11-2016 16:09 20-11-2016 06:40  
29 Agra-Sikar 1 Line 400 kV PGCIL 19-11-2016 16:10 20-11-2016 07:23  
30 Jodhpur II-Merta 1 Line 400 kV RRVPNL 19-11-2016 19:05 20-11-2016 06:44  
31 Ratangarh-Suratgarh 1 Line 400 kV RRVPNL 19-11-2016 19:20 ** **  
32 Bhiwadi-Neemrana 2 Line 400 kV PGCIL 19-11-2016 19:33 20-11-2016 07:04  
33 Heerapura-Hindaun II Line 400 kV RRVPNL 19-11-2016 19:53 20-11-2016 06:03  
34 Abdullapur-Karchamwangtoo 1 Line 400 kV JPL 19-11-2016 20:05 20-11-2016 05:34  
35 Chamera pool-Jalandhar 2 Line 400 kV PGCIL 19-11-2016 20:22 21-11-2016 05:41  
36 Parbati Pool-Parbati(3)-1 Line 400 kV PGCIL 19-11-2016 20:22 20-11-2016 00:50  
37 Abdullapur-Panchkula 1 Line 400 kV PGCIL 19-11-2016 20:24 20-11-2016 05:47  
38 Koldam(NTPC)-Ludhiana(PG) -2 Line 400 kV PKTCL 19-11-2016 20:26 ** **  
39 Amritsar-Parb-pol 1 Line 400 kV PGCIL 19-11-2016 20:30 ** **  
40 Jhakri-Panchkula 1 Line 400 kV PGCIL 19-11-2016 20:32 20-11-2016 05:23  
41 Nallagarh(PG)-Parbati Pool(PG) Line 400 kV PKTCL 19-11-2016 20:36 ** **  
42 Nallagarh-Patiala 2 Line 400 kV PGCIL 19-11-2016 20:50 20-11-2016 05:56  
43 Jhakri(SJVNL)-Karchamwangtoo(JP) 1 Line 400 kV JPHYDRO 19-11-2016 21:20 21-11-2016 05:27  
44 Ballabgarh-Mainpuri 1 Line 400 kV PGCIL 19-11-2016 21:25 20-11-2016 06:50  
45 Nallagarh(PG)-Rampur(SJVNL) -1 Line 400 kV PGCIL 19-11-2016 21:26 20-11-2016 05:13  
46 Ballabgarh(PG)-Bamnauli(DTL) 2 Line 400 kV DTL 19-11-2016 21:27 20-11-2016 07:58  
47 Abdullapur-Kurukshetra(PG) 2 Line 400 kV PGCIL 19-11-2016 21:50 21-11-2016 05:49  
48 Panchkula-Patiala 1 Line 400 kV PGCIL 19-11-2016 21:52 ** **  
49 Ludhiana-Patiala 2 Line 400 kV PGCIL 19-11-2016 21:52 20-11-2016 08:48  
50 Hisar-Moga Line 400 kV PGCIL 19-11-2016 21:54 ** **  
51 Chamera I(NHPC)-Jalandhar(PG) 2 Line 400 kV PGCIL 19-11-2016 21:55 21-11-2016 06:27  
52 Agra-Jaipur South-1 Line 400 kV PGCIL 19-11-2016 22:03 20-11-2016 07:02  
53 Patiala(PG)-Patran(PTCL) 2 Line 400 kV PGCIL 19-11-2016 22:05 ** **  
54 Baspa(HP)-Karchamwangtoo(JP) 1 Line 400 kV JPHYDRO 20-11-2016 01:04 21-11-2016 11:05  
55 Agra-Ballabgarh Line 400 kV PGCIL 20-11-2016 02:19 20-11-2016 06:56  
56 Dehar (BBMB)-Rajpura (400kV) (PSEB) Line 400 kV BBMB 20-11-2016 02:32 20-11-2016 07:15  
57 Koldam(NTPC)-Ludhiana(PG) -1 Line 400 kV PKTCL 20-11-2016 02:35 20-11-2016 06:04  
58 Daultabad-Dhanonda ckt-1 Line 400 kV HVPNL 20-11-2016 02:45 20-11-2016 07:05  
59 Ballabgarh-Kanpur 1 Line 400 kV PGCIL 20-11-2016 03:17 20-11-2016 07:14  
60 Ajmer II-Didwana Line 400 kV RRVPNL 20-11-2016 12:15 ** **  
61 Ratangarh-Suratgarh 2 Line 400 kV RRVPNL 20-11-2016 14:52 ** **  
62 Agra-Sikar 1 Line 400 kV PGCIL 20-11-2016 15:18 21-11-2016 05:58  
63 Akal-Jodhpur II Line 400 kV RRVPNL 20-11-2016 15:30 ** **  
64 Bikaner-Didwana 1 Line 400 kV RRVPNL 20-11-2016 16:11 21-11-2016 06:32  
65 Jodhpur II-Merta 1 Line 400 kV RRVPNL 20-11-2016 16:12 21-11-2016 06:29  
66 Ballabgarh-Kanpur 1 Line 400 kV PGCIL 20-11-2016 16:49 21-11-2016 05:54  
67 Heerapura-Hindaun II Line 400 kV RRVPNL 20-11-2016 19:30 21-11-2016 06:18  
68 Kota(PG)-Merta(RVPNL) 1 Line 400 kV PGCIL 20-11-2016 19:56 21-11-2016 06:34  
69 Neemrana-Sikar 2 Line 400 kV PGCIL 20-11-2016 20:02 21-11-2016 09:10  
70 Bhiwadi-Neemrana 1 Line 400 kV PGCIL 20-11-2016 20:04 21-11-2016 05:47  
71 Heerapura-Merta Line 400 kV RRVPNL 20-11-2016 20:08 21-11-2016 06:27  
72 Agra-Jaipur South-1 Line 400 kV PGCIL 20-11-2016 20:26 21-11-2016 09:46  
73 Agra-Bassi 1 Line 400 kV PGCIL 20-11-2016 20:27 21-11-2016 06:27  
74 Abdullapur-Panchkula 2 Line 400 kV PGCIL 20-11-2016 20:28 21-11-2016 06:10  
75 Nallagarh-Patiala 2 Line 400 kV PGCIL 20-11-2016 20:29 21-11-2016 05:27  
76 Ballabgarh-Mainpuri 1 Line 400 kV PGCIL 20-11-2016 20:29 21-11-2016 05:51  
77 Fatehpur-Mainpuri 1 Line 400 kV PGCIL 20-11-2016 20:30 ** **  
78 Agra(PG)-Auraiya(NTPC) 2 Line 400 kV PGCIL 20-11-2016 20:32 21-11-2016 05:48  
79 Jhakri-Panchkula 1 Line 400 kV PGCIL 20-11-2016 20:33 21-11-2016 05:56  
80 Nallagarh(PG)-Rampur(SJVNL) -1 Line 400 kV PGCIL 20-11-2016 20:39 21-11-2016 05:20  
81 Manesar-Neemrana 1 Line 400 kV PGCIL 20-11-2016 20:55 21-11-2016 05:52  
82 Ballabgarh(PG)-Bamnauli(DTL) 2 Line 400 kV DTL 20-11-2016 20:59 21-11-2016 06:05  
83 Ludhiana-Patiala 1 Line 400 kV PGCIL 20-11-2016 21:10 ** **  
84 Panchkula-Patiala 2 Line 400 kV PGCIL 20-11-2016 21:16 21-11-2016 06:38  
** - Line shall be closed subject to voltage permissibility