Reports


 

POWER GRID CORPORATION OF INDIA LTD.
Northern Regional Load Despatch Center
18-A, Qutub Institutional Area
New Delhi 110 016

Generating Unit Outage Report for 03.04.2006


Generating Unit Outage Report:

Sr. No. Station Unit No. Capacity (MW) Outage Date Outage Time Expected Date of Restoration Reason Of Outage
A. Central Sector
1 RAPP ( A ) 1 100 09.10.2004 22.58 -------- Station fault.
2 NJPC 2 250 28.10.2005 08.00 -------- Annual maintenance.
3 DADRI ( GT ) 1 130 01.04.2006 02.49 03.04.2006 Gas prassure problem
4 NAPP 1 220 31.10.2005 23.57 30.10.2006 Replacement of coolant channels.
5 ANTA(GT) 2 89 21.03.2006 00.09 23.04.2006 Major VOH inspection.
6 DEHAR 5 165 16.02.2006 09.15 24.05.2006 Capital maintenance.
7 RIHAND 3 500 01.04.2006 00.40 12.04.2006 Overhauling ' before PG test.
8 RIHAND 1 500 24.03.2006 21.02 31.04.2006 Generator Excitation problem.
9
10
11
12
13
14
15
B. State Sector
1 MALANA ( HEP ) IPP 1 & 2 86 20.01.2006 10.00 01.05.2006 Annual maintenance.
2 PANIPAT 3 110 01.01.2006 21.2 -------- Turbine vibration high.
3 RSD "1 2 3 4" 600 28.03.2006
4 PANIPAT 5 210 26.02.2006 02.17 10.04.2006 Annual maintenance.
5 BHATINDA 1 110 06.03.2006 19.00 30.09.2006 Renovation.
6 BHATINDA 3 110 11.03.2006 20.35 11.04.2006 Annual maintenance.
7 BASPA (3 x 100) "1 2 3" 300 19.01.2006 07.25
8 OBRA 12 200 27.03.2006 01.02 12.05.2006 Maintenance work.
9 ANPARA 2 210 26.03.2006 06.56 05.04.2006 Gen.Transformer problem (Bushing damaged).
10 OBRA 10 200 29.03.2006 02.38 06.04.2006 Boiler tube leakage.
11 OBRA 11 200 03.04.2006 05.28 03.04.2006 Tripped in jerk.
12
13
14
15