POWER GRID CORPORATION OF INDIA LTD.
Northern Regional Load Despatch Center
18-A, Qutub Institutional Area
New Delhi 110 016

Generating Unit Outage Report for 23.04.2006


Generating Unit Outage Report:

Sr. No. Station Unit No. Capacity (MW) Outage Date Outage Time Expected Date of Restoration Reason Of Outage
A. Central Sector
1 RAPP ( A ) 1 100 09.10.2004 22.58 -------- Station fault.
2 NJPC 2 250 28.10.2005 08.00 -------- Annual maintenance.
3 NAPP 1 220 31.10.2005 23.57 30.10.2006 Replacement of coolant channels.
4 AURAIYA ( GT ) 3 111 22.04.2006 01.14 17.05.2006 Major inspection & Overhauling.
5 DEHAR 5 165 16.02.2006 09.15 24.05.2006 Capital maintenance.
6 RIHAND 1 500 24.03.2006 21.02 30.04.2006 Generator Excitation problem.
7 NJPC 1 250 29.03.2006 15.35 ------------ Annual maintenance.
8 AURAIYA ( ST ) 2 109 22.04.2006 00.36 12.05.2006 Major inspection & Overhauling.
9 TANDA 4 110 12.04.2006 09.07 30.04.2006 Maintenance.
10 NJPC 3 250 14.04.2006 11.00 24.04.2006 Shaft seal problem.
11 SINGRAULI 6 500 17.04.2006 23.52 02.06.2006 Annual maintenance.
12 BHAKRA(R) 10 153 07.04.2006 07.30 27.04.2006 Pen stock gate maintenance.
13
14
15
B. State Sector
1 PANIPAT 3 110 01.01.2006 21.2 -------- Turbine vibration high.
2 RSD 1 to 4 600 28.03.2006 08:00 30.04.2006 Head work problem.
3 BHATINDA 1 110 06.03.2006 19.00 30.09.2006 Renovation.
4 OBRA 9 200 21.04.2006 13.17 23.04.2006 Air preheater problem.
5 BASPA (3 x 100) 1 to 3 300 19.01.2006 07.25 01.05.2006 Damage in Baspa S/yard due to landslide.
6 ANPARA 2 210 26.03.2006 06.56 30.04.2006 Gen.Transformer problem (Bushing damaged).
7 ROPAR 6 210 16.04.2006 01.00 01.05.2006 Annual maintenance.
8 PANIPAT 6 210 09.04.2006 08.36 19.05.2006 Annual maintenance.