| S.No | RefNo/ AprNo |
Application no | Utilities | FromDate | ToDate | Quantum | Route |
|---|---|---|---|---|---|---|---|
| 1 | Dec-05/AP-1571 27-Dec-05 |
PTC/OA/NR/1105 dt15-Dec-05 |
PTC GRIDCO -DTL |
01-Mar-06 | 31-Mar-06 | 1700-2300: 200 MW | ER-NR |
| 2 | Dec-05/AP-1572 27-Dec-05 |
PTC/OA/NR/1107 dt15-Dec-05 |
PTC BSEB -AVVNL |
01-Mar-06 | 31-Mar-06 | 0000-1700: 100 MW 1700-2300: 0 MW 2300-2400: 100 MW |
ER-NR |
| 3 | Dec-05/AP-1573 27-Dec-05 |
PTC/OA/NR/1106 dt15-Dec-05 |
PTC GRIDCO -JVVNL |
01-Mar-06 | 31-Mar-06 | 0000-2400: 200 MW | ER-NR |
| 4 | Dec-05/AP-1574 27-Dec-05 |
CC/NVVN/OA/12/600 dt16-Dec-05 |
NVVN MeSEB -HPGCL |
01-Feb-06 | 31-Mar-06 | 1700-2300: 20 MW | NER-ER-NR Radial |
| 5 | Dec-05/AP-1575 27-Dec-05 |
CC/NVVN/OA/12/603 dt16-Dec-05 |
NVVN KSEB -HPGCL |
01-Mar-06 | 17-Mar-06 | 0000-1700: 100 MW 1700-2300: 0 MW 2300-2400: 100 MW |
SR-WR-NR |
| 6 | Dec-05/AP-1576 27-Dec-05 |
CC/NVVN/OA/12/599 dt16-Dec-05 |
NVVN Tripura -HPGCL |
01-Feb-06 | 31-Mar-06 | 1700-2300: 25 MW | NER-ER-NR Radial |
| 7 | Feb-06/AP-2203 27-Feb-06 |
01/03/2006 dt26-Feb-06 |
HPSEB PSEB -HPSEB |
01-Mar-06 | 15-Mar-06 | 0000-2400: 100 MW | ---- |
| 8 | Feb-06/AP-2210 28-Feb-06 |
231 dt25-Feb-06 |
RPPC DTL -RPPC |
01-Mar-06 | 31-Mar-06 | 0000-0500: 200 MW 2300-2400: 200 MW |
---- |
| 9 | Feb-06/AP-2211 28-Feb-06 |
17/2005 dt27-Feb-06 |
DTL RPPC -DTL |
01-Mar-06 | 31-Mar-06 | 0630-1230: 100 MW | ---- |
| 10 | Feb-06/AP-2212 28-Feb-06 |
13-COM-B(P) dt27-Feb-06 |
UPCL PSEB -UPCL |
01-Mar-06 | 10-Mar-06 | 0000-2400: 30 MW | ---- |
| 11 | Feb-06/AP-2213 28-Feb-06 |
15-COM-B(H) dt27-Feb-06 |
UPCL HPGCL -UPCL |
01-Mar-06 | 10-Mar-06 | 0000-2400: 40 MW | ---- |
| 12 | Feb-06/AP-2214 28-Feb-06 |
PTC/OA/1495D dt28-Feb-06 |
PTC DVC -PSEB |
01-Mar-06 | 01-Mar-06 | 0000-1700: 50 MW 1700-2300: 0 MW 2300-2400: 50 MW |
ER-NR |
| 13 | Mar-06/AP-2215 01-Mar-06 |
PTC/OA/1497D dt01-Mar-06 |
PTC DVC -PSEB |
02-Mar-06 | 02-Mar-06 | 0000-1700: 50 MW 1700-2300: 0 MW 2300-2400: 50 MW |
ER-NR |
| S.No | RefNo/ AprNo |
Application no | Utilities | FromDate | ToDate | Quantum | Route |
|---|---|---|---|---|---|---|---|
| 14 | Mar-06/AP-2216 01-Mar-06 |
CC/NVVN/OA/02/1059 dt01-Mar-06 |
NVVN DADRI_L -UPPCL |
02-Mar-06 | 02-Mar-06 | 0000-2400: 40 MW | ---- |
| 15 | Mar-06/AP-2217 01-Mar-06 |
CC/NVVN/OA/02/1058 dt01-Mar-06 |
NVVN AURAIYA_L -UPPCL |
02-Mar-06 | 02-Mar-06 | 0000-2400: 70 MW | ---- |
| 16 | Mar-06/AP-2218 01-Mar-06 |
CC/NVVN/OA/02/1057 dt01-Mar-06 |
NVVN ANTA_L -UPPCL |
02-Mar-06 | 02-Mar-06 | 0000-2400: 60 MW | ---- |
| 17 | Mar-06/AP-2219 02-Mar-06 |
PTC/OA/1499D dt02-Mar-06 |
PTC DVC -PSEB |
03-Mar-06 | 03-Mar-06 | 0000-1700: 50 MW 1700-2300: 0 MW 2300-2400: 50 MW |
ER-NR |
| 18 | Mar-06/AP-2220 02-Mar-06 |
CC/NVVN/OA/03/1060 dt02-Mar-06 |
NVVN ANTA_L -UPPCL |
03-Mar-06 | 03-Mar-06 | 0000-2400: 65 MW | ---- |
| 19 | Mar-06/AP-2221 02-Mar-06 |
CC/NVVN/OA/031062 dt02-Mar-06 |
NVVN DADRI_L -UPPCL |
03-Mar-06 | 03-Mar-06 | 0000-2400: 25 MW | ---- |
| 20 | Mar-06/AP-2222 02-Mar-06 |
CC/NVVN/OA/03/1061 dt02-Mar-06 |
NVVN AURAIYA_L -UPPCL |
03-Mar-06 | 03-Mar-06 | 0000-2400: 80 MW | ---- |
| 21 | Mar-06/AP-2223 03-Mar-06 |
PTC/OA/1501D dt03-Mar-06 |
PTC DVC -PSEB |
04-Mar-06 | 04-Mar-06 | 0000-1700: 50 MW 1700-2300: 0 MW 2300-2400: 50 MW |
ER-NR |
| 22 | Mar-06/AP-2224 03-Mar-06 |
LEUL/OA/118 dt03-Mar-06 |
LEUL DTL -PSEB |
04-Mar-06 | 04-Mar-06 | 0000-0600: 200 MW | ---- |
| 23 | Mar-06/AP-2225 03-Mar-06 |
CC/NVVN/OA/03/1063 dt03-Mar-06 |
NVVN ANTA_L -UPPCL |
04-Mar-06 | 04-Mar-06 | 0000-2400: 70 MW | ---- |
| 24 | Mar-06/AP-2226 03-Mar-06 |
CC//NVVN/OA/03/1064 dt03-Mar-06 |
NVVN ANTA_L -UPPCL |
04-Mar-06 | 04-Mar-06 | 0000-2400: 100 MW | ---- |
| 25 | Mar-06/AP-2227 03-Mar-06 |
CC/NVVN/OA/03/1065 dt03-Mar-06 |
NVVN DADRI_L -UPPCL |
04-Mar-06 | 04-Mar-06 | 0000-2400: 80 MW | ---- |
| 26 | Mar-06/AP-2228 04-Mar-06 |
LEUL/OA/119 dt04-Mar-06 |
LEUL DTL -PSEB |
05-Mar-06 | 05-Mar-06 | 0000-0600: 200 MW | ---- |
| S.No | RefNo/ AprNo |
Application no | Utilities | FromDate | ToDate | Quantum | Route |
|---|---|---|---|---|---|---|---|
| 27 | Mar-06/AP-2229 04-Mar-06 |
CC/NVVN/OA/03/1066 dt04-Mar-06 |
NVVN ANTA_L -UPPCL |
05-Mar-06 | 05-Mar-06 | 0000-2400: 85 MW | ---- |
| 28 | Mar-06/AP-2230 04-Mar-06 |
CC/NVVN/OA/03/1067 dt04-Mar-06 |
NVVN AURAIYA_L -UPPCL |
05-Mar-06 | 05-Mar-06 | 0000-2400: 70 MW | ---- |
| 29 | Mar-06/AP-2231 04-Mar-06 |
CC/NVVN/OA/03/1068 dt04-Mar-06 |
NVVN DADRI_L -UPPCL |
05-Mar-06 | 05-Mar-06 | 0000-2400: 65 MW | ---- |
| 30 | Mar-06/AP-2232 05-Mar-06 |
CC/NVVN/OA/03/1069 dt05-Mar-06 |
NVVN ANTA_L -UPPCL |
06-Mar-06 | 06-Mar-06 | 0000-2400: 65 MW | ---- |
| 31 | Mar-06/AP-2233 05-Mar-06 |
CC/NVVN/OA/03/1070 dt05-Mar-06 |
NVVN AURAIYA_L -UPPCL |
06-Mar-06 | 06-Mar-06 | 0000-2400: 50 MW | ---- |
| 32 | Mar-06/AP-2234 05-Mar-06 |
CC/NVVN/OA/03/1071 dt05-Mar-06 |
NVVN DADRI_L -UPPCL |
06-Mar-06 | 06-Mar-06 | 0000-2400: 115 MW | ---- |
| 33 | Mar-06/AP-2235 05-Mar-06 |
LEUL/OA/120 dt05-Mar-06 |
LEUL DTL -PSEB |
06-Mar-06 | 06-Mar-06 | 0000-0600: 200 MW | ---- |
| 34 | Mar-06/AP-2236 06-Mar-06 |
LEUL/OA/121 dt06-Mar-06 |
LEUL DTL -PSEB |
07-Mar-06 | 07-Mar-06 | 0000-0600: 200 MW | ---- |
| 35 | Mar-06/AP-2237 06-Mar-06 |
CC/NVVN/OA/03/1072 dt06-Mar-06 |
NVVN ANTA_L -UPPCL |
07-Mar-06 | 07-Mar-06 | 0000-2400: 65 MW | ---- |
| 36 | Mar-06/AP-2238 06-Mar-06 |
CC/NVVN/OA/03/1073 dt06-Mar-06 |
NVVN AURAIYA_L -UPPCL |
07-Mar-06 | 07-Mar-06 | 0000-2400: 65 MW | ---- |
| 37 | Mar-06/AP-2239 06-Mar-06 |
CC/NVVN/OA/03/1074 dt06-Mar-06 |
NVVN DADRI_L -UPPCL |
07-Mar-06 | 07-Mar-06 | 0000-2400: 120 MW | ---- |
| 38 | Mar-06/AP-2240 07-Mar-06 |
LEUL/OA/122 dt07-Mar-06 |
LEUL DTL -PSEB |
08-Mar-06 | 08-Mar-06 | 0000-0600: 200 MW | ---- |
| 39 | Mar-06/AP-2241 07-Mar-06 |
CC/NVVN/OA/03/1077 dt07-Mar-06 |
NVVN ANTA_L -UPPCL |
08-Mar-06 | 08-Mar-06 | 0000-2400: 55 MW | ---- |
| S.No | RefNo/ AprNo |
Application no | Utilities | FromDate | ToDate | Quantum | Route |
|---|---|---|---|---|---|---|---|
| 40 | Mar-06/AP-2242 07-Mar-06 |
CC/NVVN/OA/03/1078 dt07-Mar-06 |
NVVN AURAIYA_L -UPPCL |
08-Mar-06 | 08-Mar-06 | 0000-2400: 30 MW | ---- |
| 41 | Mar-06/AP-2243 07-Mar-06 |
CC/NVVN/OA/03/1079 dt07-Mar-06 |
NVVN DADRI_L -UPPCL |
08-Mar-06 | 08-Mar-06 | 0000-2400: 50 MW | ---- |
| 42 | Mar-06/AP-2244 08-Mar-06 |
LEUL/OA/123 dt08-Mar-06 |
LEUL DTL -PSEB |
09-Mar-06 | 09-Mar-06 | 0000-0600: 200 MW | ---- |
| 43 | Mar-06/AP-2245 08-Mar-06 |
CC/NVVN/OA/03/1081 dt08-Mar-06 |
NVVN ANTA_L -UPPCL |
09-Mar-06 | 09-Mar-06 | 0000-2400: 50 MW | ---- |
| 44 | Mar-06/AP-2246 08-Mar-06 |
CC/NVVN/OA/03/1082 dt08-Mar-06 |
NVVN AURAIYA_L -UPPCL |
09-Mar-06 | 09-Mar-06 | 0000-2400: 45 MW | ---- |
| 45 | Mar-06/AP-2247 08-Mar-06 |
CC/NVVN/OA/03/1083 dt08-Mar-06 |
NVVN DADRI_L -UPPCL |
09-Mar-06 | 09-Mar-06 | 0000-2400: 50 MW | ---- |
| 46 | Mar-06/AP-2255 10-Mar-06 |
16/Com-B(H) dt09-Mar-06 |
UPCL HPGCL -UPCL |
11-Mar-06 | 12-Mar-06 | 0000-1700: 30 MW 1700-2300: 0 MW 2300-2400: 30 MW |
---- |
| 47 | Mar-06/AP-2255 10-Mar-06 |
16/Com-B(H) dt09-Mar-06 |
UPCL HPGCL -UPCL |
13-Mar-06 | 13-Mar-06 | 0000-1700: 30 MW 1700-2300: 0 MW 2300-2400: 15 MW |
---- |
| 48 | Mar-06/AP-2254 10-Mar-06 |
14/Com-B(H) dt09-Mar-06 |
UPCL PSEB -UPCL |
11-Mar-06 | 20-Mar-06 | 0000-2400: 40 MW | ---- |
| 49 | Mar-06/AP-2248 09-Mar-06 |
LEUL/OA/124 dt09-Mar-06 |
LEUL DTL -PSEB |
10-Mar-06 | 10-Mar-06 | 0000-0600: 120 MW | ---- |
| 50 | Mar-06/AP-2249 09-Mar-06 |
LEUL/OA/125 dt09-Mar-06 |
LEUL DTL -HPGCL |
10-Mar-06 | 10-Mar-06 | 0000-0600: 80 MW | ---- |
| 51 | Mar-06/AP-2252 09-Mar-06 |
CC/NVVN/OA/03/1086 dt09-Mar-06 |
NVVN AURAIYA_L -UPPCL |
10-Mar-06 | 10-Mar-06 | 0000-2400: 70 MW | ---- |
| 52 | Mar-06/AP-2250 09-Mar-06 |
CC/NVVN/OA/03/1085 dt09-Mar-06 |
NVVN ANTA_L -UPPCL |
10-Mar-06 | 10-Mar-06 | 0000-2400: 60 MW | ---- |
| S.No | RefNo/ AprNo |
Application no | Utilities | FromDate | ToDate | Quantum | Route |
|---|---|---|---|---|---|---|---|
| 53 | Mar-06/AP-2251 09-Mar-06 |
CC/NVVN/OA/03/1087 dt09-Mar-06 |
NVVN DADRI_L -UPPCL |
10-Mar-06 | 10-Mar-06 | 0000-2400: 60 MW | ---- |
| 54 | Mar-06/AP-2253 10-Mar-06 |
LEUL/OA/126 dt10-Mar-06 |
LEUL DTL -PSEB |
11-Mar-06 | 11-Mar-06 | 0000-0600: 200 MW | ---- |
| 55 | Mar-06/AP-2257 15-Mar-06 |
02/03/2006 dt14-Mar-06 |
HPSEB PSEB -HPSEB |
16-Mar-06 | 31-Mar-06 | 0000-2400: 100 MW | ---- |
| 56 | Mar-06/AP-2258 20-Mar-06 |
15/Com-B(P) dt18-Mar-06 |
UPCL PSEB -UPCL |
21-Mar-06 | 30-Mar-06 | 0000-2400: 30 MW | ---- |
| 57 | Mar-06/AP-2269 29-Mar-06 |
AEL/PT/Trans/2005- 06/1311 dt29-Mar-06 |
ADANI WBSEB -PSEB |
30-Mar-06 | 30-Mar-06 | 0600-1600: 50 MW | ER-NR |
| 58 | Mar-06/AP-2271 30-Mar-06 |
AEL/PT/Trans/2005-06/1324 dt30-Mar-06 |
ADANI WBSEB -PSEB |
31-Mar-06 | 31-Mar-06 | 0100-0930: 50 MW | ER-NR |